Heramb Aarambha RERA Details - P51700051941, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Heramb Aarambha under registration P51700051941 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700051941
  • Project Name Heramb Aarambha - Phase 2
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Vangani (CT)
  • Original Completion 31 December 2027
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 5,340.0
  • Total Buildings/Towers 2
  • Documents 47 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 13 July 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name HERAMB ENTERPRISES

Promoters, Co-promoters & Members

NameRoleAddress
VIDYADHAR NANDKUMAR PALANDEPartnerThane, MAHARASHTRA
BHANUDAS YASHWANT GAIKWADPartnerThane, MAHARASHTRA
GANESH MADHUKAR DESHMUKHPartnerThane, MAHARASHTRA
SOMNATH MOTIRAM PALANDEPartnerThane, MAHARASHTRA
MANISH JAYWANT SHELARPartnerMumbai City, MAHARASHTRA
PRAKASH BARKU GAWALIPartnerThane, MAHARASHTRA
Dilip Motiram DalalPartnerThane, MAHARASHTRA
Vaishali Ganesh DeshmukhPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Heramb Aarambha - Phase 2 Building Type - A 2 42 8 7 7 56 NA
Heramb Aarambha - Phase 2 Building Type - B 1 43 8 7 7 56 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 112
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 84 units · avg area 35.23 Sq.mt.
2 BHK 28 units · avg area 46.69 Sq.mt.
  • Building Type - A
  • Building Type - B
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 45.91 14 8
1BHK 34.05 21 16
1BHK 35.31 7 4
1BHK 36.87 14 10
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 80.0% Water Supply 80.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 90.0%
Storm Water Drains 90.0% Landscaping & Tree Planting 60.0% Street Lighting 60.0%
Community Buildings 70.0% Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 60.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 50.0% Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 80.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Building Type - A
  • Building Type - B
Building Type - A · Overall Progress 82%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 A Details Of Encumbrances Concerned To Finance.Pdf
5 2 A Details Of Encumbrances Concerned To Finance.Pdf
6 1 B Details Of Encumbrances Concerned To Legal.Pdf
7 2 B Details Of Encumbrances Concerned To Legal.Pdf
8 1 Copy Of Layout Approval (In Case Of Layout).Pdf
9 1 Building Plan Approval NA Order For Plotted Development.Pdf
10 2 Building Plan Approval NA Order For Plotted Development.Pdf
11 3 Building Plan Approval NA Order For Plotted Development.Pdf
12 4 Building Plan Approval NA Order For Plotted Development.Pdf
13 5 Building Plan Approval NA Order For Plotted Development.Pdf
14 1 Commencement Certificates NA Order For Plotted Development.Pdf
15 1 Declaration About Commencement Certificate.Pdf
16 1 Declaration In FORM B.Pdf
17 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
18 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
19 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
20 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
21 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
22 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
23 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
24 1 CERSAI Details.Pdf
25 1 Disclosure Of Sold Booked Inventory.Pdf
26 2 Disclosure Of Sold Booked Inventory.Pdf
27 3 Disclosure Of Sold Booked Inventory.Pdf
28 4 Disclosure Of Sold Booked Inventory.Pdf
29 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
30 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
31 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
32 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
33 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
34 1 Proforma Of Allotment Letter.Pdf
35 1 Proforma Of Agreement For Sale.Pdf
36 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
37 1 Deviation Report With Respect To Allotment Letter.Pdf
38 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
50 Form 1.Pdf
51 Form 2.Pdf
52 Form 3.Pdf
53 Disclosure Of Sold And Booked Inventory.Pdf
78 Withdrawal Update Form 1.Pdf
82 Withdrawal Update Form 2.Pdf
86 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0001806
Branch Address LOTUS HOUSE SHOP NO 5-12 KATRAP ROAD BADLAPUR EAST
Country/City