K M Horizon Palms III RERA Details - P51700028504, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for K M Horizon Palms III under registration P51700028504 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700028504
  • Project Name HORIZON PALMS - III
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 30 December 2024
  • Revised Completion 30 December 2024
  • Project Area (in Sq.mt.) 1,150.0
  • Total Buildings/Towers 2
  • Documents 59 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 March 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name KM DEVELOPERS
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
HORIZON PALMS 2OWALE THANE-4006151353.18CompletedResidential / Group Housing2492021-10-302021-02-18NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
HORIZON PALMS - III WING - A 36 0 9 0 0 NA
HORIZON PALMS - III WING - B 0 0 8 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 74
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 37 units · avg area 37.07 Sq.mt.
2 BHK 20 units · avg area 46.86 Sq.mt.
Shop 17 units · avg area 13.82 Sq.mt.
  • WING - A
  • WING - B
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 10.72 1 1
Shop 16.59 1 0
Shop 11.07 1 1
Shop 8.27 1 1
Shop 10.23 1 1
Shop 12.62 1 1
Shop 15.68 1 1
2BHK 47.16 7 6
2BHK 47.49 7 6
1BHK 37.57 7 5
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 95.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 95.0% Fire Protection And Fire Safety Requirements 40.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 35.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • WING - A
  • WING - B
WING - A · Overall Progress 89%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work80%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 2 Details Of Encumbrances.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 2 Copy Of Layout Approval (In Case Of Layout).Pdf
7 1 Building Plan Approval NA Order For Plotted Development.Pdf
8 2 Building Plan Approval NA Order For Plotted Development.Pdf
9 3 Building Plan Approval NA Order For Plotted Development.Pdf
10 1 Commencement Certificates NA Order For Plotted Development.Pdf
11 2 Commencement Certificates NA Order For Plotted Development.Pdf
12 3 Commencement Certificates NA Order For Plotted Development.Pdf
13 1 Declaration In FORM B.Pdf
14 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
15 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
16 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
17 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
18 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
19 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
20 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
21 8 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
22 9 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
23 10 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
24 11 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
25 12 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
26 13 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
27 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
28 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
29 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
30 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
31 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
32 6 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
33 7 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
34 8 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
35 9 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
36 10 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
37 11 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
38 12 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
39 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
40 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
41 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
42 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
43 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
44 6 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
45 7 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
46 8 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
47 9 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
48 10 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
49 11 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
50 12 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
51 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
52 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
53 2 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
54 1 Proforma Of Allotment Letter.Pdf
55 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
56 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
66 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank DCB BANK LIMITED
IFSC DCBL0000086
Branch Address MUCHHALA POLYTECHNIC EC KASARVADVALI G B ROAD THANE W 400615
Country/City