Kalpatru Shalibhadra RERA Details - P51700007732, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kalpatru Shalibhadra under registration P51700007732 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700007732
  • Project Name KALPATRU ENTERPRISES
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Bhiwandi
  • Village Bhiwandi (M Corp.)
  • Original Completion 31 March 2019
  • Revised Completion 31 August 2024
  • Project Area (in Sq.mt.) 1,558.0
  • Total Buildings/Towers 1
  • Documents 36 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 17 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2019 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 August 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
KALPATRU HEIGHTKAMATGHAR TALUKA BHIWANDI3304CompletedResidential / Group Housing1412012-09-032012-12-04NoNA
KALPATRU ARCADEKAMATGHAR BHIWANDI1632.5CompletedIndustrial1322017-03-012017-04-29NoNA
KALPATRU GARDENKAMATGHAR BHIWANDI6134CompletedResidential / Group Housing2942016-06-202017-02-04NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
KALPATRU ENTERPRISES SHALIBHADRA 12 12 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 42
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 14 units · avg area 73.87 Sq.mt.
3 BHK 12 units · avg area 93.59 Sq.mt.
Shop 16 units · avg area 30.51 Sq.mt.
  • SHALIBHADRA
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 33.09 4 3
2BHK 81.69 2 1
3BHK 93.59 12 11
2BHK 78.07 2 2
Shop 39.41 2 2
Shop 34.29 2 2
2BHK 71.47 10 8
Shop 22.96 2 2
Shop 27.7 2 2
Shop 27.79 2 2
Shop 25.74 2 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 75.0% Water Supply 40.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 60.0%
Storm Water Drains 65.0% Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 75.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 80.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SHALIBHADRA
SHALIBHADRA · Overall Progress 60%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
In Progress
% Work90%
Slabs of Super Structure
In Progress
% Work8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work60%
Sanitary Fittings within the flats / premises
In Progress
% Work25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work40%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 2 Details Of Encumbrances.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval (IOD).Pdf
7 2 Building Plan Approval (IOD).Pdf
8 1 Commencement Certificates NA Order For Plotted Development.Pdf
9 2 Commencement Certificates NA Order For Plotted Development.Pdf
10 1 Declaration About Commencement Certificate.Pdf
11 1 Declaration In FORM B.Pdf
12 2 Declaration In FORM B.Pdf
13 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
14 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
15 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
16 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
17 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
18 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
19 1 Disclosure Of Sold Booked Inventory.Pdf
20 1 CERSAI Details.Pdf
21 2 Disclosure Of Sold Booked Inventory.Pdf
22 1 Certificates Of CA (Form 3).Pdf
23 2 Certificates Of CA (Form 3).Pdf
24 3 Certificates Of CA (Form 3).Pdf
25 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2017 18).Pdf
26 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
27 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
28 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
29 2 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
30 1 Proforma Of Allotment Letter.Pdf
31 2 Proforma Of Allotment Letter.Pdf
32 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
33 1 Other.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.