Lodha Palava Aquaville Series Milano D G RERA Details - P51700010109, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Lodha Palava Aquaville Series Milano D G under registration P51700010109 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700010109
  • Project Name PALVA MILANO D, G
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Khoni
  • Original Completion 30 March 2023
  • Revised Completion 30 March 2023
  • Project Area (in Sq.mt.) 2,017.0
  • Total Buildings/Towers 2
  • Documents 51 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 24 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 March 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 March 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Palava Dwellers Private Limited

Promoters, Co-promoters & Members

NameRoleAddress
Rajendra LodhaChairpersonMumbai City, MAHARASHTRA
Rajendra LodhaChairpersonMumbai City, MAHARASHTRA
Rajendra LodhaChairpersonMumbai City, MAHARASHTRA
Rajendra LodhaChairpersonMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
PALVA MILANO D, G MILANO D 9 61 18 0 0 NA
PALVA MILANO D, G MILANO G 9 61 18 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 146
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 7 units · avg area 44.43 Sq.mt.
2 BHK 83 units · avg area 49.63 Sq.mt.
3 BHK 56 units · avg area 59.31 Sq.mt.
  • MILANO D
  • MILANO G
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2 BHK Ultima 55.1 1 1
2 BHK Ultima 54.98 13 0
2 BHK Ultima 55.03 4 0
1 BHK 39.48 2 1
2 BHK Ultima 45.12 10 0
3 BHK Optima 59.74 18 18
2 BHK Ultima 49.05 22 22
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Sports Complex % not reported Club House % not reported Closing Parking 100.0%
Temple % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • MILANO D
  • MILANO G
MILANO D · Overall Progress 73%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

2 1 Copy Of The Legal Title Report.Pdf
Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 3 Copy Of The Legal Title Report.Pdf
5 1 Details Of Encumbrances.Pdf
6 2 Details Of Encumbrances.Pdf
7 3 Details Of Encumbrances.Pdf
8 4 Details Of Encumbrances.Pdf
9 5 Details Of Encumbrances.Pdf
10 6 Details Of Encumbrances.Pdf
11 1 Copy Of Layout Approval (In Case Of Layout).Pdf
12 1 Building Plan Approval (IOD).Pdf
13 2 Building Plan Approval (IOD).Pdf
14 3 Building Plan Approval (IOD).Pdf
15 1 Commencement Certificates NA Order For Plotted Development.Pdf
16 2 Commencement Certificates NA Order For Plotted Development.Pdf
17 3 Commencement Certificates NA Order For Plotted Development.Pdf
18 4 Commencement Certificates NA Order For Plotted Development.Pdf
19 5 Commencement Certificates NA Order For Plotted Development.Pdf
20 1 Declaration In FORM B.Pdf
21 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
22 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
23 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
24 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
25 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
26 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
27 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
28 1 Form 2A.Pdf
29 2 Form 2A.Pdf
30 3 Form 2A.Pdf
31 4 Form 2A.Pdf
32 1 Disclosure Of Sold Booked Inventory.Pdf
33 2 Disclosure Of Sold Booked Inventory.Pdf
34 3 Disclosure Of Sold Booked Inventory.Pdf
35 4 Disclosure Of Sold Booked Inventory.Pdf
36 1 Certificates Of CA (Form 3).Pdf
37 2 Certificates Of CA (Form 3).Pdf
38 3 Certificates Of CA (Form 3).Pdf
39 4 Certificates Of CA (Form 3).Pdf
40 1 Certificates Of CA (Form 5).Pdf
41 2 Certificates Of CA (Form 5).Pdf
42 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
43 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
44 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
45 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
46 1 Proforma Of Allotment Letter.Pdf
47 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
48 1 Architect’S Certificate On Completion Of Project (Form 4).Pdf
49 1 Status Of Formation Of Legal Entity (Society Co Op Etc.).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank YES BANK
IFSC YESB0000419
Branch Address India Bulls Parel Mumbai
Country/City