residential Ready to Move Source: rera.mh

Moraya Madhur Maa CHS RERA Details - P51700022416, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Moraya Madhur Maa CHS under registration P51700022416 in Thane, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700022416
  • Project Name MADHUR MAA CO-OPERATIVE
  • Project Type Residential
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Thane
  • Taluka Ambarnath
  • Village Ambarnath (R)
  • Original Completion 30 March 2024
  • Project Area (in Sq.mt.) 573.57
  • Total Buildings/Towers 1
  • Documents 28 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 20 September 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 March 2024 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name MORAYA DEVELOPERS
Other Description NA

Promoters, Co-promoters & Members

NameRole
VISHWANATH RAMCHANDRA PANVELKARAuthorized Signatory
VISHWANATH RAMCHANDRA PANVELKARPartner
HARSHAL AVINASH GAWANDALKARPartner
ABHIJIT ARUN SHETYEPartner
DEVEN AJIT ADARKARPartner
DEVEN AJIT ADARKARAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
MADHUR MAA CO-OPERATIVE MADHUR MAA CO-OPERATIVE HSG SOCIETY LTD 2023-03-31 0 1 0 5 3 0 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 34
Configurations 12
Inventory Type RESIDENTIAL
Configuration Distribution
SHOP1 1 unit · avg area 22.95 Sq.mt.
1RK 4 units · avg area 22.82 Sq.mt.
1 BHK 17 units · avg area 33.51 Sq.mt.
SHOP2 1 unit · avg area 13.55 Sq.mt.
2 BHK 4 units · avg area 42.55 Sq.mt.
SHOP3 1 unit · avg area 9.53 Sq.mt.
SHOP4 1 unit · avg area 11.82 Sq.mt.
SHOP5 1 unit · avg area 16.55 Sq.mt.
SHOP6 1 unit · avg area 16.55 Sq.mt.
SHOP7 1 unit · avg area 17.29 Sq.mt.
SHOP8 1 unit · avg area 19.58 Sq.mt.
STLITS 1 unit · avg area 35.64 Sq.mt.
  • MADHUR MAA CO-OPERATIVE HSG SOCIETY LTD
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
SHOP1 22.95 1 0
SHOP2 13.55 1 0
SHOP8 19.58 1 0
STLITS 35.64 1 0
1RK 22.82 4 4
1BHK 30.80 4 4
1BHK 31.95 4 4
1BHK 32.63 4 4
1BHK 37.67 4 4
2BHK 42.55 4 3
1BHK 37.45 1 1
SHOP3 9.53 1 1
SHOP4 11.82 1 1
SHOP5 16.55 1 1
SHOP6 16.55 1 1
SHOP7 17.29 1 1
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 3 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting % not reported Energy Management % not reported
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply % not reported Sewerage 100%
Storm Water Drains 100% Landscaping Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • MADHUR MAA CO-OPERATIVE HSG SOCIETY LTD
MADHUR MAA CO-OPERATIVE HSG SOCIETY LTD · Overall Progress 97%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Complete
% Work100%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work67%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
2 A Details Of Encumbrances Concerned To Finance
1 B Details Of Encumbrances Concerned To Legal
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval / NA Order For Plotted Development
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
1 Engineer’S Certificate On Cost Incurred On Project (Form 2)
2 Engineer’S Certificate On Cost Incurred On Project (Form 2)
3 Engineer’S Certificate On Cost Incurred On Project (Form 2)
4 Engineer’S Certificate On Cost Incurred On Project (Form 2)
1 Disclosure Of Sold/ Booked Inventory
1 CERSAI Details
1 Disclosure Of Interest In Other Real Estate Organizations
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021-22)
1 Proforma Of Allotment Letter
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0000457
Country/City