Oberoi Garden City Thane RERA Details - PR1331012400078, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Oberoi Garden City Thane under registration PR1331012400078 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PR1331012400078
  • Project Name OGC Thane Phase 1
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 30 June 2031
  • Revised Completion 30 June 2031
  • Project Area (in Sq.mt.) 54,070.0
  • Total Buildings/Towers 3
  • Documents 11 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 October 2024 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2031 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2031 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individual Name Oberoi Realty Limited
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Exquisite by Oberoi RealtyExquisite Oberoi Garden City Off Western Express Highway Goregaon East Mumbai 400 0633116.79CompletedResidential / Group Housing38022014-12-312015-05-11NoNA
Priviera by Oberoi RealtyPriviera Junction of Sarojini Road and Main Avenue Road Santacruz West Mumbai Maharashtra 400 054264.8CompletedResidential / Group Housing1122015-05-022015-05-02NoNA
Commerz 2Commerz 2 International Business Park Oberoi Garden City Off Western Express Highway Goregaon East Mumbai 400 0631790.3CompletedCommercial1—2013-12-312013-12-31NoNA
Elysian Tower A95/4/B/4 pt of village Dindoshi, Off Western Express Highway, Goregaon East, Mumbai, Maharashtra 4000631497.08OngoingResidential / Group Housing1—2027-06-30—NoNA

Promoters, Co-promoters & Members

NameRole
Saumil Ashwin DaruWhole-time Director & CFO
Bindu Ranvir OberoiDirector
Bindu Ranvir OberoiDirector
Vikas Ranvir OberoiDirector
Prafulla Premsukh ChhajedDirector
Karamjit Singh KalsiNon Executive Independent Director
Anil HarishNon Executive Independent Director
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Survey Number CTS NO. 172/1, 176/1, 176/5, 176/6, 176/7, 283/7/C, 283/8/C

Boundary Details

Boundaries East Partly S No 176-1 partly S No 172-1 partly S No 176-5 Boundaries West Partly S No 283-C-7 and 8 Partly S No 172-1 and partly S No 176-1
Boundaries South Partly S No 172-1 and partly S No 176-1 Boundaries North 40 m wide Pokhran Road No 2 partly S No 176-1 partly S No 172-1 and partly S No 176-7

RERA Coordinates

Latitude, Longitude 19.2183616, 72.9687397

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
OGC Thane Phase 1 Tower - A 5 9 9 0 0 NA
OGC Thane Phase 1 Tower - B 474 70 100 62 472 NA
OGC Thane Phase 1 Tower - C 459 68 68 60 462 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 11.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 44.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 1.0%
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Tower - A
  • Tower - B
  • Tower - C
Tower - A · Overall Progress 36%
Stilt Floor
Not Started
% Work0%
Excavation
In Progress
% Work95%
Basement (if any)
Complete
% Work100%
Podiums (if any)
In Progress
% Work7%
Plinth
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work43%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work27%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work21%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work1%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Form 1.Pdf
2 Form 2.Pdf
3 Form 3.Pdf
4 Disclosure Of Sold And Booked Inventory.Pdf
13 Withdrawal Update Form 1.Pdf
17 Withdrawal Update Form 2.Pdf
21 Withdrawal Update Form 3.Pdf
25 Form 2A (FY 2025 2026).Pdf
26 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000281
Branch Address ICICI Bank Ltd., Ground Floor, Vrindavan, Building No. 15, Shivdham Complex, Dindoshi, Malad East, Mumbai.400097, Maharashtra
Country/City