Om Sai Kanishk RERA Details - P51700012436, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Om Sai Kanishk under registration P51700012436 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700012436
  • Project Name SAI KANISHK PHASE II
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 31 March 2019
  • Revised Completion 30 June 2025
  • Project Area (in Sq.mt.) 1,171.65
  • Total Buildings/Towers 3
  • Documents 45 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 01 September 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2019 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name Om Sai Infra & Om Sai Group

Promoters, Co-promoters & Members

NameAddress
OM SAI INFRAThane, MAHARASHTRA
MAHESH PATELThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SAI KANISHK PHASE II B4 23 21 13 13 13 62 NA
SAI KANISHK PHASE II B5 15 16 13 13 13 37 NA
SAI KANISHK PHASE II B6 26 11 14 14 14 81 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 168
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 60 units · avg area 63.16 Sq.mt.
2 BHK 83 units · avg area 78.67 Sq.mt.
One One and half BHK 14 units · avg area 81.12 Sq.mt.
Shop 11 units · avg area 33.39 Sq.mt.
  • B4
  • B5
  • B6
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 61.32 26 22
2BHK 90.39 33 31
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • B4
  • B5
  • B6
B4 · Overall Progress 48%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
In Progress
% Work90%
Slabs of Super Structure
In Progress
% Work83%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 2 Building Plan Approval (IOD).Pdf
7 1 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration About Commencement Certificate.Pdf
9 1 Declaration In FORM B.Pdf
10 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
11 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
12 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
13 2 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
14 3 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
15 4 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
16 5 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
17 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
18 2 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
19 3 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
20 4 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
21 1 Disclosure Of Sold Booked Inventory.Pdf
22 2 Disclosure Of Sold Booked Inventory.Pdf
23 3 Disclosure Of Sold Booked Inventory.Pdf
24 4 Disclosure Of Sold Booked Inventory.Pdf
25 1 Certificates Of CA (Form 3).Pdf
26 2 Certificates Of CA (Form 3).Pdf
27 3 Certificates Of CA (Form 3).Pdf
28 4 Certificates Of CA (Form 3).Pdf
29 5 Certificates Of CA (Form 3).Pdf
30 6 Certificates Of CA (Form 3).Pdf
31 1 Certificates Of CA (Form 5).Pdf
32 2 Certificates Of CA (Form 5).Pdf
33 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
34 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
35 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
36 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
37 1 Proforma Of Allotment Letter.Pdf
38 2 Proforma Of Allotment Letter.Pdf
39 Form 1.Pdf
40 Form 2.Pdf
41 Form 3.Pdf
42 Disclosure Of Sold And Booked Inventory.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0000004
Branch Address JEEVAN PRAKASH BUILDING GROUND FLOOR SIR P M ROAD FORT MUMBAI 400001
Country/City