residential Under Construction Source: rera.mh

Pragati Om Gulmohar RERA Details - P51700054917, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Pragati Om Gulmohar under registration P51700054917 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700054917
  • Project Name Pragati Om Gulmohar
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village DOMBIVLI
  • Original Completion 30 September 2027
  • Revised Completion 30 September 2027
  • Project Area (in Sq.mt.) 1,103.0
  • Total Buildings/Towers 1
  • Documents 38 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 15 February 2024 Expected commencement of civil works and foundation on site.
Original Completion 30 September 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 September 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name PRAGATI HOMES

Promoters, Co-promoters & Members

NameRoleAddress
VIRAL ISHWAR PATELPartnerMumbai Suburban, MAHARASHTRA
ISHWAR PACHAN PATELPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Pragati Om Gulmohar PRAGATI OM GULMOHAR 10 30 9 9 8 48 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • PRAGATI OM GULMOHAR
PRAGATI OM GULMOHAR · Overall Progress 89%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work80%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 1 B Details Of Encumbrances Concerned To Legal.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval NA Order For Plotted Development.Pdf
7 1 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration About Commencement Certificate.Pdf
9 1 Declaration In FORM B.Pdf
10 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
14 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
15 1 CERSAI Details.Pdf
16 2 CERSAI Details.Pdf
17 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
18 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
19 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
20 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
21 1 Proforma Of Allotment Letter.Pdf
22 1 Proforma Of Agreement For Sale.Pdf
23 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
24 1 Deviation Report With Respect To Allotment Letter.Pdf
25 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
32 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
33 Form 1.Pdf
34 Form 2.Pdf
35 Form 3.Pdf
36 Disclosure Of Sold And Booked Inventory.Pdf
41 Self Declaration Of Quarterly Progress.Pdf
57 Withdrawal Update Form 1.Pdf
63 Withdrawal Update Form 2.Pdf
69 Withdrawal Update Form 3.Pdf
75 Form 5 (FY 2023 2024).Pdf
76 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF BARODA
IFSC BARB0DBGHTE
Branch Address Saikrupa Society, Ghatkopar East, Mumbai 400077
Country/City