residential Under Construction Source: rera.mh

Precious Icon RERA Details - P51700076725, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Precious Icon under registration P51700076725 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700076725
  • Project Name PRECIOUS ICON
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Ambarnath(M Cl)
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 2,600.0
  • Total Buildings/Towers 2
  • Documents 41 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 21 June 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name RKR Construction

Promoters, Co-promoters & Members

NameRoleAddress
Haresh Bhajanlal MattaPartnerThane, MAHARASHTRA
Jaydeep Ashok BhoirPartnerThane, MAHARASHTRA
Swaraj Ashok BhoirPartnerThane, MAHARASHTRA
Navin Ramesh BansalPartnerThane, MAHARASHTRA
Ishwarlal Nathu ChavanPartnerThane, MAHARASHTRA
Suresh Dhanraj DhamejaPartnerThane, MAHARASHTRA
Deepak Murlidhar MattaPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
PRECIOUS ICON B1 0 47 9 9 0 33 NA
PRECIOUS ICON B2 0 46 9 9 0 36 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 69
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 31 units · avg area 35.71 Sq.mt.
2 BHK 29 units · avg area 47.31 Sq.mt.
Shop 7 units · avg area 13.12 Sq.mt.
Shop LandOwner 2 units · avg area 9.38 Sq.mt.
  • B1
  • B2
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 9.63 1 1
2BHK LandOwner 46.88 1 0
2BHK LandOwner 48.38 3 0
2BHK LandOwner 49.61 3 0
2BHK 46.88 6 2
1BHK LandOwner 33.86 2 0
1BHK 33.86 5 0
Shop 18.8 1 1
Shop 13.67 1 1
2BHK LandOwner 46.67 1 0
Shop 15.43 1 1
2BHK 48.38 4 1
2BHK 49.61 4 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • B1
  • B2
B1 · Overall Progress 61%
Stilt Floor
Not Started
% Work0%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work65%
Sanitary Fittings within the flats / premises
In Progress
% Work65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work25%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

30 2 Other – Legal.Pdf
31 3 Other – Legal.Pdf
32 4 Other – Legal.Pdf
Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 1 B Details Of Encumbrances Concerned To Legal.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval NA Order For Plotted Development.Pdf
7 1 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration About Commencement Certificate.Pdf
9 1 Declaration In FORM B.Pdf
10 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
13 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
14 1 CERSAI Details.Pdf
15 2 CERSAI Details.Pdf
16 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
17 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
18 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
19 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
20 4 Disclosure Of Interest In Other Real Estate Organizations.Pdf
21 5 Disclosure Of Interest In Other Real Estate Organizations.Pdf
22 6 Disclosure Of Interest In Other Real Estate Organizations.Pdf
23 7 Disclosure Of Interest In Other Real Estate Organizations.Pdf
24 1 Proforma Of Agreement For Sale.Pdf
25 1 Proforma Of Allotment Letter.Pdf
26 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
27 1 Deviation Report With Respect To Allotment Letter.Pdf
28 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
29 1 Other – Legal.Pdf
33 5 Other – Legal.Pdf
34 1 Other – Technical.Pdf
43 Withdrawal Update Form 1.Pdf
46 Withdrawal Update Form 2.Pdf
49 Withdrawal Update Form 3.Pdf
52 Form 5 (FY 2024 2025).Pdf
53 Occupational Certificate.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0005278
Branch Address Shop No 7,8,9,10,11 and 12, Vishwajeet Empire NX, Palegaon Road, Next to Royal Flora, Behind Anand S
Country/City