residential Under Construction Source: rera.mh

Sai Shrushti Leela RERA Details - P51700078596, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sai Shrushti Leela under registration P51700078596 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700078596
  • Project Name SAI SHRUSHTI LEELA
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 31 December 2027
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 4,204.82
  • Total Buildings/Towers 3
  • Documents 44 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 27 December 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SAI SHRUSHTI ENTERPRISES

Promoters, Co-promoters & Members

NameRoleAddressEmail
ABHIJIT BHARAT ALIMKARPartnerThane, MAHARASHTRA-
MAHAVIR PRAVIN MEHTAPartnerThane, MAHARASHTRAejN0l2Ftt9wEH0WKaUj5yrdAavkCXyBOY7ppKAcYQA3kKeweCpMN3a9ao/x1yY21
NILKANTH YADAV BHAGATPartnerThane, MAHARASHTRAejN0l2Ftt9wEH0WKaUj5yrdAavkCXyBOY7ppKAcYQA3kKeweCpMN3a9ao/x1yY21
ANIL GANESH BHAGATPARTNERThane, MAHARASHTRAejN0l2Ftt9wEH0WKaUj5yrdAavkCXyBOY7ppKAcYQA3kKeweCpMN3a9ao/x1yY21

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SAI SHRUSHTI LEELA BUILDING 2 0 0 1 1 1 1 NA
SAI SHRUSHTI LEELA BUILDING 1 105 0 20 20 19 148 NA
SAI SHRUSHTI LEELA BUILDING 3 103 48 20 20 19 180 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING 2
  • BUILDING 1
  • BUILDING 3
BUILDING 2 · Overall Progress 55%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Proforma Of Allotment Letter.Pdf
7 1 Declaration In FORM B.Pdf
8 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
9 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
10 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
11 1 Commencement Certificates NA Order For Plotted Development.Pdf
12 2 Commencement Certificates NA Order For Plotted Development.Pdf
13 1 Building Plan Approval NA Order For Plotted Development.Pdf
14 2 Other – Legal.Pdf
15 1 Other – Legal.Pdf
16 1 Declaration About Commencement Certificate.Pdf
17 1 CERSAI Details.Pdf
18 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
19 2 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
20 1 Deviation Report With Respect To Allotment Letter.Pdf
21 1 B Details Of Encumbrances Concerned To Legal.Pdf
22 2 B Details Of Encumbrances Concerned To Legal.Pdf
23 1 Other – Finance.Pdf
24 1 Other – Technical.Pdf
25 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
26 1 Proforma Of Agreement For Sale.Pdf
27 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
28 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
29 2 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
30 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
34 1 Disclosure Of Sold Booked Inventory.Pdf
35 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
36 Form 1.Pdf
37 Form 2.Pdf
38 Form 3.Pdf
39 Disclosure Of Sold And Booked Inventory.Pdf
40 Others.Pdf
41 Withdrawal Update Form 1.Pdf
47 Withdrawal Update Form 2.Pdf
53 Withdrawal Update Form 3.Pdf
59 Form 2A (FY 2024 2025).Pdf
60 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BHARAT COOPERATIVE BANK MUMBAI LIMITED
IFSC BCBM0000091
Branch Address GROUND FLOOR, SHREE KRISHNA PARK, DIVA-SHILL ROAD, THANE DISTRICT, DIVA EAST- 400612
Country/City