Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.mh

Salasar Greens RERA Details - P51700000586, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Salasar Greens under registration P51700000586 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700000586
  • Project Name SALASAR GREENS
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village BHAYANDAR
  • Original Completion 25 December 2022
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 7,850.0
  • Total Buildings/Towers 1
  • Documents 60 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 18 July 2017 Expected commencement of civil works and foundation on site.
Original Completion 25 December 2022 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SALASAR ESTATE DEVELOPERS LLP
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
SALASAR ASSOCIATESOPP. D'MART.2930CompletedMixed112015-02-092015-05-13NoNA

Promoters, Co-promoters & Members

NameRoleAddress
SALASAR NORTH EAST BUILDERS LLP .PARTNERThane, MAHARASHTRA
RUBY STRUCTURES PRIVATE LIMITED .PARTNERPalghar, MAHARASHTRA
KASTURI BUILDCONLLP .PARTNERThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SALASAR GREENS SALASAR GREENS 6 8 9 9 7 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 38
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 16 units · avg area 35.36 Sq.mt.
2 BHK 19 units · avg area 48.32 Sq.mt.
Shop 3 units · avg area 24.18 Sq.mt.
  • SALASAR GREENS
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 35.09 15 13
2BHK 48.32 19 8
Shop 27.87 1 1
Shop 22.34 2 1
1BHK 39.46 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SALASAR GREENS
SALASAR GREENS · Overall Progress 36%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 1 Declaration About Commencement Certificate.Pdf
8 1 Declaration In FORM B.Pdf
9 2 Declaration In FORM B.Pdf
10 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
14 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
15 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
16 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
17 5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
18 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
19 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
20 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
21 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
22 2 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
23 1 Disclosure Of Sold Booked Inventory.Pdf
24 1 CERSAI Details.Pdf
25 2 Disclosure Of Sold Booked Inventory.Pdf
26 3 Disclosure Of Sold Booked Inventory.Pdf
27 1 Certificates Of CA (Form 3).Pdf
28 2 Certificates Of CA (Form 3).Pdf
29 3 Certificates Of CA (Form 3).Pdf
30 4 Certificates Of CA (Form 3).Pdf
31 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2017 18).Pdf
32 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
33 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
34 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
35 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
36 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
37 1 Proforma Of Allotment Letter.Pdf
42 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
43 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2024 25).Pdf
46 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
47 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
48 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
49 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
52 7 Certificates Of CA (Form 3).Pdf
53 6 Certificates Of CA (Form 3).Pdf
54 5 Certificates Of CA (Form 3).Pdf
59 7 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
60 6 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
68 4 Disclosure Of Sold Booked Inventory.Pdf
69 5 Disclosure Of Sold Booked Inventory.Pdf
70 6 Disclosure Of Sold Booked Inventory.Pdf
71 7 Disclosure Of Sold Booked Inventory.Pdf
72 Form 1.Pdf
73 Form 2.Pdf
74 Form 3.Pdf
75 Disclosure Of Sold And Booked Inventory.Pdf
80 Form 2A (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
IFSC BACB0000003
Branch Address SAROVAR BUILDING, PAPDY, VASAI WEST, DIST PALGHAR 401207
Country/City