Shree Garden Estate RERA Details - P51700052971, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shree Garden Estate under registration P51700052971 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700052971
  • Project Name Garden Estate Phase -II
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Ambivali Tarf Chon
  • Original Completion 31 March 2025
  • Revised Completion 30 September 2025
  • Project Area (in Sq.mt.) 3,600.0
  • Total Buildings/Towers 1
  • Documents 43 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 06 October 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 September 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SHREE BALAJI DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
VIJAYNARAYAN SHITLAPRASAD UPADHYAYPartnerMumbai City, MAHARASHTRA
RAMNARAYAN SHITLAPRASAD UPADHYAYPartnerMumbai City, MAHARASHTRA
BHARAT MALIKPartnerThane, MAHARASHTRA
KRISHANK MALIKPartnerThane, MAHARASHTRA
VINAYKUMAR SABHAJIT DUBEYPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Garden Estate Phase -II Garden Estate Phase -II 174 10 6 6 6 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting 50.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space 100.0% Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Garden Estate Phase -II
Garden Estate Phase -II · Overall Progress 83%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work75%
Sanitary Fittings within the flats / premises
In Progress
% Work50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 B Details Of Encumbrances Concerned To Legal.Pdf
6 2 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval NA Order For Plotted Development.Pdf
9 2 Building Plan Approval NA Order For Plotted Development.Pdf
10 1 Commencement Certificates NA Order For Plotted Development.Pdf
11 2 Commencement Certificates NA Order For Plotted Development.Pdf
12 1 Declaration About Commencement Certificate.Pdf
13 1 Declaration In FORM B.Pdf
14 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
15 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
16 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
17 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
18 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
19 1 CERSAI Details.Pdf
20 1 Disclosure Of Sold Booked Inventory.Pdf
21 2 Disclosure Of Sold Booked Inventory.Pdf
22 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
23 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
24 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
25 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
26 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
27 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
28 1 Proforma Of Agreement For Sale.Pdf
29 1 Proforma Of Allotment Letter.Pdf
30 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
31 1 Deviation Report With Respect To Allotment Letter.Pdf
32 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
37 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
44 1 Other – Technical.Pdf
47 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
48 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
49 Form 1.Pdf
50 Form 2.Pdf
51 Form 3.Pdf
52 Disclosure Of Sold And Booked Inventory.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank CENTRAL BANK OF INDIA
IFSC CBIN0283773
Branch Address Shiv Sadan House No 298, Opp Sateswar Nath Temple, Mainpune Link Road, Tisagaon, Kalyan East
Country/City