Shree Nalini CHS RERA Details - P51700055539, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shree Nalini CHS under registration P51700055539 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700055539
  • Project Name SHREE NALINI C.H.S LIMITED
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Original Completion 13 December 2025
  • Revised Completion 13 December 2025
  • Project Area (in Sq.mt.) 570.0
  • Total Buildings/Towers 1
  • Documents 39 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 02 April 2024 Expected commencement of civil works and foundation on site.
Original Completion 13 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 13 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SHREE ASHTAVINAYAK INFRA

Promoters, Co-promoters & Members

NameRoleAddress
Praveen Shriram RanePartnerThane, MAHARASHTRA
Narendrakumar Madhukar RanePartnerBuldana, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SHREE NALINI C.H.S LIMITED SHREE NALINI CHS LTD 0 0 6 6 6 29 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 29
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 13 units · avg area 30.53 Sq.mt.
1RK 7 units · avg area 22.06 Sq.mt.
2 BHK 5 units · avg area 44.17 Sq.mt.
Shop 4 units · avg area 12.10 Sq.mt.
  • SHREE NALINI CHS LTD
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 24.77 1 1
Shop 11.76 1 0
1BHK 34.37 1 1
1RK 19.48 1 1
2BHK 45.15 2 2
1BHK 24.74 1 1
1BHK 29.88 1 1
1RK 24.38 1 0
1RK 18.72 1 0
Shop 13.23 1 0
1BHK 33.49 1 0
Shop 8.72 1 0
1BHK 33.47 2 2
1BHK 32.19 2 2
Shop 14.7 1 0
2BHK 43.51 3 3
1BHK 34.99 1 0
1RK 19.19 1 0
1RK 24.3 1 0
1RK 30.14 1 0
1RK 18.18 1 1
1BHK 24.25 2 1
1BHK 34.79 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SHREE NALINI CHS LTD
SHREE NALINI CHS LTD · Overall Progress 76%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 A Details Of Encumbrances Concerned To Finance.Pdf
5 2 A Details Of Encumbrances Concerned To Finance.Pdf
6 1 B Details Of Encumbrances Concerned To Legal.Pdf
7 2 B Details Of Encumbrances Concerned To Legal.Pdf
8 1 Copy Of Layout Approval (In Case Of Layout).Pdf
9 1 Building Plan Approval NA Order For Plotted Development.Pdf
10 1 Commencement Certificates NA Order For Plotted Development.Pdf
11 1 Declaration About Commencement Certificate.Pdf
12 1 Declaration In FORM B.Pdf
13 2 Declaration In FORM B.Pdf
14 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
15 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
16 1 CERSAI Details.Pdf
17 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
18 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
19 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
20 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
21 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
22 1 Proforma Of Allotment Letter.Pdf
23 1 Proforma Of Agreement For Sale.Pdf
24 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
25 1 Deviation Report With Respect To Allotment Letter.Pdf
26 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
27 1 Other – Legal.Pdf
28 1 Other – Technical.Pdf
30 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
33 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
35 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
36 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
40 Withdrawal Update Form 1.Pdf
45 Withdrawal Update Form 2.Pdf
50 Withdrawal Update Form 3.Pdf
55 Form 5 (FY 2024 2025).Pdf
56 Occupational Certificate.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0000457
Branch Address Sitai Sadan Suryodaya Chs, Ambernath Station Road, Near Idbi Bank Ltd, Ambernath, Thane, Maharashtra
Country/City