RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P51700008791
- Project Name SHREENIWASA RESIDENCY
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Thane
- Taluka Ambarnath
- Village Badlapur (M Cl)
- Original Completion 31 December 2021
- Revised Completion 30 December 2022
- Project Area (in Sq.mt.) 2,770
- Total Buildings/Towers 3
- Documents 23 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| NIKHIL NANDKUMAR DALAL | Authorized Signatory |
| NIKHIL NANDKUMAR DALAL | Partner |
| NAMRATA NANDKUMAR DALAL | Partner |
| NILESH KONDIRAM CHAMBAVANE | Partner |
| SIDDHI NILESH CHAMBAVANE | Partner |
| NILAKSHI KONDIRAM CHAMBAVANE | Partner |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| SHREENIWASA RESIDENCY | SHREENIWASA RESIDENCY WING A | 2021-12-31 | 1 | 1 | 0 | 8 | 1 | 0 | 0 |
| SHREENIWASA RESIDENCY | SHREENIWASA RESIDENCY WING B | 2021-12-31 | 0 | 1 | 0 | 8 | 1 | 0 | 1 |
| SHREENIWASA RESIDENCY | SHREENIWASA RESIDENCY WING C | 2021-12-31 | 0 | 1 | 0 | 5 | 0 | 0 | 0 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- SHREENIWASA RESIDENCY WING A
- SHREENIWASA RESIDENCY WING B
- SHREENIWASA RESIDENCY WING C
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1BHK | 26.36 | 15 | 12 |
| 1BHK | 26.41 | 8 | 7 |
| 1BHK | 26.6 | 1 | 1 |
| 1BHK | 26.69 | 8 | 6 |
| 1BHK | 26.89 | 7 | 3 |
| 1BHK | 27.77 | 2 | 2 |
| 1BHK | 30.34 | 8 | 4 |
| 1BHK | 30.98 | 6 | 5 |
| 2BHK | 38.82 | 6 | 0 |
| SHOP | 43.4 | 1 | 1 |
| SHOP | 9.9 | 1 | 1 |
| SHOP | 16.17 | 1 | 1 |
| SHOP | 17.04 | 1 | 1 |
| SHOP | 18.64 | 1 | 1 |
| SHOP | 20.13 | 1 | 1 |
| SHOP | 25.62 | 1 | 1 |
| SHOP | 25.77 | 2 | 2 |
| 1BHK | 26.05 | 6 | 4 |
| SHOP | 47.85 | 1 | 1 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1BHK | 25.56 | 1 | 1 |
| 1BHK | 27.32 | 7 | 0 |
| 1BHK | 28.4 | 1 | 1 |
| 1BHK | 31.28 | 7 | 1 |
| 1BHK | 31.58 | 7 | 3 |
| 1RK | 18.61 | 1 | 0 |
| 1RK | 19.61 | 7 | 1 |
| 1RK | 19.64 | 8 | 1 |
| 1RK | 20.45 | 8 | 1 |
| 1BHK | 24.48 | 7 | 3 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1RK | 21.43 | 5 | 5 |
| 1RK | 22.15 | 5 | 5 |
| 1BHK | 27.02 | 5 | 5 |
| 1BHK | 28.46 | 5 | 5 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 0 | 0 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths % not reported | Water Conservation Rainwater Harvesting % not reported | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements % not reported | Electrical Meter Room Substation Receivingstation % not reported | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking % not reported | Water Supply % not reported | Sewerage % not reported |
| Storm Water Drains % not reported | Landscaping Tree Planting % not reported | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- SHREENIWASA RESIDENCY WING A
- SHREENIWASA RESIDENCY WING B
- SHREENIWASA RESIDENCY WING C
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | CENTRAL BANK OF INDIA |
|---|---|
| IFSC | CNRB0000215 |