Shri Ratna Darshan Height RERA Details - PM1330002500202, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shri Ratna Darshan Height under registration PM1330002500202 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PM1330002500202
  • Project Name Ratna Darshan Height
  • Project Type Mixed
  • Project Status New Launch
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village DOMBIVLI
  • Original Completion 31 March 2028
  • Revised Completion 31 March 2028
  • Project Area (in Sq.mt.) 643.6
  • Total Buildings/Towers 1
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 04 July 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 March 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Shri Panchsheel Developers

Promoters, Co-promoters & Members

NameRoleAddress
Chetan Devilal SinghviPartnerThane, MAHARASHTRA
Sohanlal Devichand JainPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Ratna Darshan Height Ratna Darshan Height 20 36 8 8 8 41 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Open Parking % not reported Internal Roads & Footpaths % not reported Water Supply % not reported
Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported Storm Water Drains % not reported Landscaping & Tree Planting % not reported
Street Lighting % not reported Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported
Solid Waste Management And Disposal % not reported Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Ratna Darshan Height
Ratna Darshan Height · Overall Progress 64%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
In Progress
% Work60%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work60%
Sanitary Fittings within the flats / premises
In Progress
% Work30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work20%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Withdrawal Update Form 1.Pdf
3 Withdrawal Update Form 2.Pdf
5 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank UCO BANK
IFSC UCBA0003365
Branch Address SHOP NO 1 4, GUPTE ROAD, NITYANAND BHAVAN ,THANE ,MAHARASHTRA PIN 421202
Country/City