Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.mh

Stonecrafters Harold CHS RERA Details - P51700053912, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Stonecrafters Harold CHS under registration P51700053912 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700053912
  • Project Name HAROLD CO-OP HOUSING SOCIETY
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Chikanghar
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 395.0
  • Total Buildings/Towers 1
  • Documents 26 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 11 December 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name STONECRAFTERS

Promoters, Co-promoters & Members

NameRoleAddress
ASHIT BALOO GARUDPartnerThane, MAHARASHTRA
JAMES SARTO MORAISPartnerviU9zWI9WLjcRylhaEKYpUEkj/g0F9cE359hxDJ78fd5LLVlfPZZo/eBwhm5AQoN, Thane, MAHARASHTRA
PRASAD SUBHASH PATILPartnerThane, MAHARASHTRA
SURAJ BHARAT PATILPartnerThane, MAHARASHTRA
ANKITA DINESH MOREPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
HAROLD CO-OP HOUSING SOCIETY HAROLD CHSL 23 0 5 8 5 21 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 14
Configurations 5
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 3 units · avg area 28.77 Sq.mt.
2 BHK 6 units · avg area 43.73 Sq.mt.
3 BHK 1 unit · avg area 56.67 Sq.mt.
4 BHK 1 unit · avg area 101.22 Sq.mt.
Shop 3 units · avg area 13.69 Sq.mt.
  • HAROLD CHSL
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 53.14 1 0
4BHK 101.22 1 0
Shop 11.87 1 0
Shop 19.65 1 0
Shop 9.54 1 0
2BHK 47.47 3 0
1BHK 28.77 3 0
3BHK 56.67 1 0
2BHK 33.42 2 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • HAROLD CHSL
HAROLD CHSL · Overall Progress 79%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work96%
Sanitary Fittings within the flats / premises
In Progress
% Work92%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work94%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 3 A Details Of Encumbrances Concerned To Finance.Pdf
6 1 B Details Of Encumbrances Concerned To Legal.Pdf
7 2 B Details Of Encumbrances Concerned To Legal.Pdf
8 3 B Details Of Encumbrances Concerned To Legal.Pdf
9 1 Copy Of Layout Approval (In Case Of Layout).Pdf
10 1 Building Plan Approval NA Order For Plotted Development.Pdf
11 1 Commencement Certificates NA Order For Plotted Development.Pdf
12 1 Declaration About Commencement Certificate.Pdf
13 1 Declaration In FORM B.Pdf
14 1 CERSAI Details.Pdf
15 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
16 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
17 1 Proforma Of Allotment Letter.Pdf
18 1 Proforma Of Agreement For Sale.Pdf
19 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
20 1 Deviation Report With Respect To Allotment Letter.Pdf
21 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
22 Withdrawal Update Form 1.Pdf
26 Withdrawal Update Form 2.Pdf
30 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank THE SHAMRAO VITHAL COOPERATIVE BANK
IFSC SVCB0000054
Branch Address SHOP NO 3B NIRAJ PARK KHADAK PADA KALYAN 421301
Country/City