residential Under Construction Source: rera.mh

Thanekar Palacio RERA Details - P51700032795, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Thanekar Palacio under registration P51700032795 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700032795
  • Project Name THANEKAR PALACIO
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 31 December 2024
  • Revised Completion 31 December 2024
  • Project Area (in Sq.mt.) 4,947.0
  • Total Buildings/Towers 2
  • Documents 87 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 29 January 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name THANEKAR REALTOR LLP

Promoters, Co-promoters & Members

NameRoleAddress
AJAY MADHUKAR THANEKARPartnerThane, MAHARASHTRA
VAISHALI AJAY THANEKARPartnerThane, MAHARASHTRA
ADVAIT AJAY THANEKARPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
THANEKAR PALACIO A WING 0 0 18 0 0 NA
THANEKAR PALACIO B WING 0 0 18 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 259
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 135 units · avg area 35.96 Sq.mt.
2 BHK 114 units · avg area 51.56 Sq.mt.
3 BHK 10 units · avg area 73.22 Sq.mt.
  • A WING
  • B WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 52.09 1 1
2BHK 51.63 14 13
1BHK 35.22 1 1
2BHK 49.46 15 14
1BHK 35.21 1 1
1BHK 35.67 2 0
3BHK 72.87 9 9
2BHK 54.29 1 0
1BHK 37.13 15 11
1BHK 36.4 30 27
2BHK 53.37 11 11
3BHK 76.34 1 0
2BHK 51.6 1 1
1BHK 36.38 14 13
1BHK 35.97 16 4
2BHK 49.5 1 0
2BHK 54.27 6 5
1BHK 37.1 1 0
2BHK 53.6 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 75.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A WING
  • B WING
A WING · Overall Progress 62%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work90%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 Details Of Encumbrances.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 2 Copy Of Layout Approval (In Case Of Layout).Pdf
7 3 Copy Of Layout Approval (In Case Of Layout).Pdf
8 4 Copy Of Layout Approval (In Case Of Layout).Pdf
9 1 Building Plan Approval NA Order For Plotted Development.Pdf
10 2 Building Plan Approval NA Order For Plotted Development.Pdf
11 3 Building Plan Approval NA Order For Plotted Development.Pdf
12 4 Building Plan Approval NA Order For Plotted Development.Pdf
13 5 Building Plan Approval NA Order For Plotted Development.Pdf
14 6 Building Plan Approval NA Order For Plotted Development.Pdf
15 7 Building Plan Approval NA Order For Plotted Development.Pdf
16 8 Building Plan Approval NA Order For Plotted Development.Pdf
17 9 Building Plan Approval NA Order For Plotted Development.Pdf
18 10 Building Plan Approval NA Order For Plotted Development.Pdf
19 11 Building Plan Approval NA Order For Plotted Development.Pdf
20 12 Building Plan Approval NA Order For Plotted Development.Pdf
21 13 Building Plan Approval NA Order For Plotted Development.Pdf
22 14 Building Plan Approval NA Order For Plotted Development.Pdf
23 15 Building Plan Approval NA Order For Plotted Development.Pdf
24 16 Building Plan Approval NA Order For Plotted Development.Pdf
25 17 Building Plan Approval NA Order For Plotted Development.Pdf
26 18 Building Plan Approval NA Order For Plotted Development.Pdf
27 19 Building Plan Approval NA Order For Plotted Development.Pdf
28 1 Commencement Certificates NA Order For Plotted Development.Pdf
29 2 Commencement Certificates NA Order For Plotted Development.Pdf
30 1 Declaration About Commencement Certificate.Pdf
31 1 Declaration In FORM B.Pdf
32 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
33 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
34 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
35 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
36 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
37 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
38 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
39 8 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
40 9 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
41 10 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
42 11 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
43 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
44 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
45 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
46 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
47 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
48 6 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
49 7 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
50 8 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
51 9 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
52 10 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
53 11 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
54 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
55 1 CERSAI Details.Pdf
56 2 CERSAI Details.Pdf
57 1 Disclosure Of Sold Booked Inventory.Pdf
58 2 Disclosure Of Sold Booked Inventory.Pdf
59 3 Disclosure Of Sold Booked Inventory.Pdf
60 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
61 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
62 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
63 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
64 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
65 6 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
66 7 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
67 8 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
68 9 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
69 10 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
70 11 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
71 12 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
72 13 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
73 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
74 2 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
75 3 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
76 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
77 1 Proforma Of Allotment Letter.Pdf
78 2 Proforma Of Allotment Letter.Pdf
79 3 Proforma Of Allotment Letter.Pdf
81 1 Architect’S Certificate On Completion Of Project (Form 4).Pdf
82 2 Architect’S Certificate On Completion Of Project (Form 4).Pdf
83 3 Architect’S Certificate On Completion Of Project (Form 4).Pdf
86 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
87 2 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
90 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
IFSC SBIN0001053