Tirupati Pooja RERA Details - P51700020271, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Tirupati Pooja under registration P51700020271 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700020271
  • Project Name TIRUPATI POOJA
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Mira-Bhayandar (M Corp.)
  • Original Completion 30 December 2024
  • Revised Completion 30 December 2024
  • Project Area (in Sq.mt.) 2,540.0
  • Total Buildings/Towers 1
  • Documents 41 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 31 March 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name OM SHREE TIRUPATI BALAJI BUILDERS

Promoters, Co-promoters & Members

NameRoleAddress
SANGEETHA PRAVIN SANGHVIPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
TIRUPATI POOJA TIUPATI POOJA 9 11 16 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 130
Configurations 8
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 118 units · avg area 39.04 Sq.mt.
GODOWN NO 1 1 unit · avg area 26.65 Sq.mt.
GODOWN NO 2 1 unit · avg area 14.53 Sq.mt.
GODOWN NO 3 1 unit · avg area 18.28 Sq.mt.
GODOWN NO 4 1 unit · avg area 23.06 Sq.mt.
GODOWN NO 5 1 unit · avg area 13.32 Sq.mt.
GODOWN NO 6 1 unit · avg area 17.72 Sq.mt.
COMMERCIAL SHOP 6 units · avg area 19.57 Sq.mt.
  • TIUPATI POOJA
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 41.66 15 11
COMMERCIAL SHOP 17.72 1 1
COMMERCIAL SHOP 35.28 1 0
GODOWN NO 3 18.28 1 0
COMMERCIAL SHOP 14.53 1 1
GODOWN NO 1 26.65 1 0
COMMERCIAL SHOP 18.28 2 2
GODOWN NO 4 23.06 1 1
GODOWN NO 5 13.32 1 1
1BHK 42.42 6 2
RESIDENTIAL 1BHK 38.98 24 3
COMMERCIAL SHOP 13.32 1 1
GODOWN NO 6 17.72 1 1
GODOWN NO 2 14.53 1 1
RESIDENTIAL 1BHK 38.24 73 56
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • TIUPATI POOJA
TIUPATI POOJA · Overall Progress 73%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 2 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval (IOD).Pdf
7 2 Building Plan Approval (IOD).Pdf
8 3 Building Plan Approval (IOD).Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 2 Commencement Certificates NA Order For Plotted Development.Pdf
11 1 Declaration About Commencement Certificate.Pdf
12 1 Declaration In FORM B.Pdf
13 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
14 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
15 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
16 4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
17 5 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
18 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
19 1 Form 2A.Pdf
20 2 Form 2A.Pdf
21 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
22 2 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
23 1 Disclosure Of Sold Booked Inventory.Pdf
24 1 Certificates Of CA (Form 3).Pdf
25 2 Certificates Of CA (Form 3).Pdf
26 3 Certificates Of CA (Form 3).Pdf
27 4 Certificates Of CA (Form 3).Pdf
28 5 Certificates Of CA (Form 3).Pdf
29 1 Certificates Of CA (Form 5).Pdf
30 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
31 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
32 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
33 1 Proforma Of Allotment Letter.Pdf
34 2 Proforma Of Allotment Letter.Pdf
35 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
36 1 Other.Pdf
37 1 Architect’S Certificate On Completion Of Project (Form 4).Pdf
38 1 Status Of Formation Of Legal Entity (Society Co Op Etc.).Pdf
40 2 Architect’S Certificate On Completion Of Project (Form 4).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank UNION BANK OF INDIA
IFSC UBIN0539287
Branch Address BHAYANDER WEST 401101
Country/City