residential Under Construction Source: rera.tg

Praneeth Pranav Daffodils RERA Details - P02200004137, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Praneeth Pranav Daffodils under registration P02200004137 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02200004137
  • Project Name PRANEETH PRANAV DAFFODILS
  • Project Type Residential
  • Project Status Under Construction
  • Original Completion 12 January 2028
  • Documents 85 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 February 2022 Expected commencement of civil works and foundation on site.
Original Completion 12 January 2028 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name VENKATA PRANEETH DEVELOPERS PRIVATE LIMITED
GST Number 36AACCV4975A1ZC
Website www.praneeth.com

Promoters, Co-promoters & Members

NameRole
KAMARAJU NARENDRA KUMARManaging Director
KAMARAJU VENKATA SUBBA NARASINGA RAODirector
KAMARAJU BHANU REKHADirector
BAKKIREDDY CHENNAREDDY CHANDRASHEKHARDirector
PATHAPATI RAMANJANEYA RAJUDirector
SAPPIDI DINESH REDDYAuthorized Signatory
MADHAVARAM SIVAIAHGARI SANDEEP RAODirector

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Slab No. of Slits Total Parking Area
PRANEETH PRANAV DAFFODILS BLOCK A 2028-01-12 0 6 1 6924
PRANEETH PRANAV DAFFODILS BLOCK B 2028-01-12 0 6 1 1
PRANEETH PRANAV DAFFODILS BLOCK C 2028-01-12 0 6 1 1
PRANEETH PRANAV DAFFODILS CLUB OUSE 2028-01-12 0 3 0 1

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 231
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 100 units · avg area 106.86 Sq.mt.
3 BHK 55 units · avg area 148.59 Sq.mt.
4 BHK 1 unit · avg area 12.00 Sq.mt.
5 BHK 75 units · avg area 126.65 Sq.mt.
  • BLOCK A
  • BLOCK B
  • BLOCK C
  • CLUB OUSE
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 2 BHK 108.79 False 1 0
GF 2.5 BHK 123.56 False 1 1
GF 2.5 BHK 120.22 False 1 1
GF 2 BHK 108.79 False 1 1
GF 2 BHK 108.79 False 1 1
GF 2 BHK 108.79 False 1 1
GF 2 BHK 108.79 False 1 1
GF 2 BHK 108.79 False 1 0
GF 2.5 BHK 123.56 False 1 0
GF 2.5 BHK 127.18 False 1 1
GF 2 BHK 108.79 False 1 1
GF 2 BHK 108.79 False 1 0
GF 2 BHK 108.79 False 1 0
GF 2 BHK 114.36 False 1 0
1 2 BHK 108.79 False 1 1
1 2 BHK 108.79 False 1 1
1 2 BHK 108.79 False 1 0
1 2 BHK 108.79 False 1 0
1 2.5 BHK 120.22 False 1 0
1 2.5 BHK 127.18 False 1 0
1 2.5 BHK 123.56 False 1 0
1 2.5 BHK 123.56 False 1 1
1 2 BHK 114.36 False 1 1
1 2 BHK 108.79 False 1 1
1 2 BHK 108.79 False 1 1
1 2 BHK 108.79 False 1 0
1 2 BHK 108.79 False 1 1
1 2 BHK 108.76 False 1 1
2 2 BHK 108.79 False 1 0
2 2 BHK 114.36 False 1 1
2 2 BHK 108.79 False 1 1
2 2 BHK 108.79 False 1 1
2 2 BHK 108.79 False 1 1
2 2 BHK 108.79 False 1 1
2 2.5 BHK 120.22 False 1 1
2 2.5 BHK 123.56 False 1 1
2 2.5 BHK 127.18 False 1 1
2 2 BHK 108.79 False 1 0
2 2 BHK 108.79 False 1 0
2 2 BHK 108.79 False 1 0
2 2 BHK 108.79 False 1 1
2 2.5 BHK 123.56 False 1 1
3 2.5 BHK 120.22 False 1 0
3 2 BHK 114.36 False 1 0
3 2.5 BHK 123.56 False 1 1
3 2 BHK 108.79 False 1 1
3 2.5 BHK 127.18 False 1 1
3 2 BHK 108.79 False 1 1
3 2 BHK 108.79 False 1 1
3 2 BHK 108.79 False 1 1
3 2 BHK 108.79 False 1 1
3 2 BHK 108.79 False 1 1
3 2 BHK 108.79 False 1 0
3 2 BHK 108.79 False 1 0
3 2 BHK 108.79 False 1 0
3 2.5 BHK 123.56 False 1 0
4 2.5 BHK 123.56 False 1 1
4 2.5 BHK 123.56 False 1 0
4 2 BHK 108.79 False 1 1
4 2 BHK 108.79 False 1 1
4 2 BHK 108.79 False 1 0
4 2 BHK 114.36 False 1 1
4 2 BHK 108.79 False 1 1
4 2.5 BHK 120.22 False 1 1
4 2 BHK 108.79 False 1 0
4 2 BHK 108.79 False 1 0
4 2.5 BHK 127.18 False 1 0
4 2 BHK 108.79 False 1 0
4 2 BHK 108.79 False 1 1
4 2 BHK 108.79 False 1 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 100% Water Supply 100% Sewerage 98%
Storm Water Drains 98% Green Strip 95% Street Lighting 95%
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water 96% Solid Waste Management Disposal 80%
Water Conservation Rainwater Harvesting 80% Energy Management 96% Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation 95% Aggregate Area Of Recreational Open Space 96%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BLOCK A
  • BLOCK B
  • BLOCK C
  • CLUB OUSE
BLOCK A · Overall Progress 100%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Complete
% Work100%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Details Of Encumbrances
Details Of Encumbrances
Details Of Encumbrances
Details Of Encumbrances
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Proforma Of The Allotment Letter And Agreement For Sale
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Status Of Formation Of Legal Entity (Society/Co Op Etc.)
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Form–1A Architects Certificate Overall Completion Of Registered Project
Country/City