- RERA Number P51700050118
- Project Status Under Construction
- District Thane
- Taluka Thane
- Project Area (in Sq.mt.) 836.86
- Total Buildings/Towers 2
- Documents 2 Verified
Timeline
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Proposed Start
15 March 2023
Expected commencement of civil works and foundation on site.
Development
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths % not reported | Water Supply % not reported | Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0% |
| Storm Water Drains % not reported | Landscaping & Tree Planting 100.0% | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage And Sullage Water 100.0% | Solid Waste Management And Disposal 100.0% |
| Water Conservation /Rain Water Harvesting 100.0% | Energy Managemcnt 80.0% | Fire Protection And Fire Safety Requirements 60.0% |
| Electrical Meter Room, Sub-station, Receiving Station 50.0% | Aggregate Area Of Recreational Open Space 50.0% | Open Parking % not reported |
Documents
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | KOTAK MAHINDRA BANK LIMITED |
|---|---|
| IFSC | KKBK0001418 |
| Branch Address | Harsh Plaza, 100ft Road, Mira Bhayander, Mira Road East, Thane 401107 |