RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P51700011840
- Project Name Ajmera Heritage - Phase 1
- Project Type Others
- Project Status Ready to Move
- State MAHARASHTRA
- District Thane
- Taluka Shahapur
- Village Khardi (CT)
- Original Completion 31 December 2015
- Revised Completion 31 March 2019
- Project Area (in Sq.mt.) 21,040
- Total Buildings/Towers 7
- Documents 89 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| Ajmera Heritage - Phase 1 | A1 Rose A and B | 2020-03-30 | 0 | 1 | 0 | 5 | 0 | 0 | 0 |
| Ajmera Heritage - Phase 1 | A2 Rose C and D | 2020-03-30 | 0 | 1 | 0 | 5 | 0 | 0 | 0 |
| Ajmera Heritage - Phase 1 | A3 Lotus A and B | 2020-03-30 | 0 | 1 | 0 | 5 | 0 | 0 | 0 |
| Ajmera Heritage - Phase 1 | A4 Lotus C and D | 2020-03-30 | 0 | 1 | 0 | 5 | 0 | 0 | 0 |
| Ajmera Heritage - Phase 1 | A5 Jasmine A and B | 2020-03-30 | 0 | 1 | 0 | 5 | 0 | 0 | 0 |
| Ajmera Heritage - Phase 1 | B1 Jasmine C and D | 2020-03-30 | 0 | 1 | 0 | 5 | 0 | 0 | 0 |
| Ajmera Heritage - Phase 1 | C1 Shops Ground and First floor | 2019-03-31 | 0 | 1 | 0 | 2 | 0 | 0 | 0 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- A1 Rose A and B
- A2 Rose C and D
- A3 Lotus A and B
- A4 Lotus C and D
- A5 Jasmine A and B
- B1 Jasmine C and D
- C1 Shops Ground and First floor
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1RK | 30.5 | 1 | 0 |
| 1RK | 27.9 | 10 | 0 |
| 2BHK | 59.1 | 10 | 4 |
| 1BHK | 38 | 37 | 7 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1RK | 30.5 | 1 | 0 |
| 1RK | 27.9 | 10 | 5 |
| 1BHK | 38 | 37 | 10 |
| 2BHK | 59.1 | 10 | 3 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1RK | 27.9 | 10 | 2 |
| 2BHK | 59.1 | 10 | 0 |
| 1RK | 30.5 | 1 | 0 |
| 1BHK | 38 | 37 | 9 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1RK | 30.5 | 1 | 0 |
| 1RK | 27.9 | 10 | 2 |
| 1BHK | 38 | 37 | 8 |
| 2BHK | 59.1 | 10 | 3 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1RK | 30.5 | 1 | 0 |
| 2BHK | 59.1 | 10 | 1 |
| 1BHK | 38 | 37 | 7 |
| 1RK | 27.9 | 10 | 3 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1RK | 30.5 | 1 | 0 |
| 1BHK | 38 | 37 | 6 |
| 2BHK | 59.1 | 10 | 4 |
| 1RK | 27.9 | 8 | 2 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| S1 | 32.6 | 1 | 0 |
| S2 | 29.15 | 1 | 0 |
| S3 and GFS5 | 58.1 | 2 | 0 |
| FFS3 upto FFS11 | 23.55 | 9 | 0 |
| FFS12 | 28.75 | 1 | 0 |
| S4 | 74.34 | 1 | 0 |
| S6 | 51.76 | 1 | 0 |
| FFS1 | 26.55 | 1 | 0 |
| FFS2 | 23.04 | 1 | 0 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 0 | 0 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 95% | Water Conservation Rainwater Harvesting 100% | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements % not reported | Electrical Meter Room Substation Receivingstation 40% | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking % not reported | Water Supply % not reported | Sewerage 50% |
| Storm Water Drains 100% | Landscaping Tree Planting 100% | Street Lighting 100% |
| Community Buildings 100% | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal 100% |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- A1 Rose A and B
- A2 Rose C and D
- A3 Lotus A and B
- A4 Lotus C and D
- A5 Jasmine A and B
- B1 Jasmine C and D
- C1 Shops Ground and First floor
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | Kotak Mahindra Bank Ltd |
|---|---|
| IFSC | KKBK0000962 |