Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Alpha Saffron Hill RERA Details - P51700028321, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Alpha Saffron Hill under registration P51700028321 in Thane, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700028321
  • Project Name SAFFRON HILLS L- WING
  • Project Type Residential
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 30 September 2023
  • Project Area (in Sq.mt.) 1,032.86
  • Total Buildings/Towers 1
  • Documents 12 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 18 February 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 September 2023 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name ALPHA COMBINES
Other Description NA

Promoters, Co-promoters & Members

NameRole
RAJESH KESHAVLAL PATELAuthorized Signatory
AVINASH DATTATRAY PATKARPartner
CHANDRIKA RAJESH PATELPartner
ALPESH KESHAVLAL PATELPartner
KIRIT RAVJI PATELPartner
MUKESH RAVJI PATELPartner
SHILESH RATILAL PATELPartner
RATILAL KARSHAN PATELPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
SAFFRON HILLS L- WING L WING 2023-03-31 0 1 0 5 0 2 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 31
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 24 units · avg area 27.07 Sq.mt.
Shop 7 units · avg area 16.44 Sq.mt.
  • L WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 16.44 7 0
1BHK 27.07 24 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting % not reported Energy Management % not reported
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply % not reported Sewerage % not reported
Storm Water Drains % not reported Landscaping Tree Planting % not reported Street Lighting % not reported
Community Buildings 50% Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • L WING
L WING · Overall Progress 0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Excavation
Not Started
% Work0%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
X number of Slabs of Super Structure
Not Started
% Work0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Not Started
% Work0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval / NA Order For Plotted Development
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration In FORM B
1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
1 Engineer’S Certificate On Cost Incurred On Project (Form 2)
1 Proforma Of Allotment Letter
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF BARODA
IFSC BARB0BADLAP
Country/City