residential Under Construction Source: rera.mh

Gurukrupa PG Vatika RERA Details - P51700080943, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Gurukrupa PG Vatika under registration P51700080943 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700080943
  • Project Name PG VATIKA WING E AND F
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 31 December 2030
  • Revised Completion 31 December 2030
  • Project Area (in Sq.mt.) 3,042.0
  • Total Buildings/Towers 2
  • Documents 45 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 August 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2030 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2030 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name GURUKRUPA ENTERPRISES

Promoters, Co-promoters & Members

NameRoleAddress
AVINASH DATTATRAY PATKARPartnerThane, MAHARASHTRA
PRACHI AJAY PATKARPartnerThane, MAHARASHTRA
AJAY DATTATRAY PATKARPartnerThane, MAHARASHTRA
JITENDRA BHARAT GADGEPartnerThane, MAHARASHTRA
GAJENDRA BHARAT GADGEPartnerThane, MAHARASHTRA
RITESH SHARAD GADGEPartnerThane, MAHARASHTRA
PARUL PARAG PATELPartnerMumbai Suburban, MAHARASHTRA
SNEHA AVINASH PATKARPartnerThane, MAHARASHTRA
DILIP AMRUTLAL PATELPartnerThane, MAHARASHTRA
JAGJIVAN KALYANBHAI VADGAMAPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
PG VATIKA WING E AND F WING E 0 83 10 8 8 63 NA
PG VATIKA WING E AND F WING F 0 104 10 8 8 79 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 142
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 127 units · avg area 29.55 Sq.mt.
1RK 5 units · avg area 22.10 Sq.mt.
LAND OWNER 1 RK 2 units · avg area 22.10 Sq.mt.
2 BHK 8 units · avg area 45.27 Sq.mt.
  • WING E
  • WING F
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
LAND OWNER 1 BHK 29.92 9 0
LAND OWNER 1 BHK 27.63 2 0
1BHK 27.63 5 0
1BHK 29.13 20 0
LAND OWNER 1 BHK 29.13 12 0
1BHK 29.92 15 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • WING E
  • WING F
WING E · Overall Progress 50%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work25%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 A Details Of Encumbrances Concerned To Finance.Pdf
4 1 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 2 Copy Of Layout Approval (In Case Of Layout).Pdf
7 3 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Proforma Of Allotment Letter.Pdf
9 1 Declaration In FORM B.Pdf
10 2 Declaration In FORM B.Pdf
11 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
14 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
15 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
16 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
17 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
18 3 Commencement Certificates NA Order For Plotted Development.Pdf
19 2 Commencement Certificates NA Order For Plotted Development.Pdf
20 1 Commencement Certificates NA Order For Plotted Development.Pdf
21 1 Building Plan Approval NA Order For Plotted Development.Pdf
22 2 Building Plan Approval NA Order For Plotted Development.Pdf
23 1 Declaration About Commencement Certificate.Pdf
24 1 CERSAI Details.Pdf
25 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
26 1 Deviation Report With Respect To Allotment Letter.Pdf
27 2 B Details Of Encumbrances Concerned To Legal.Pdf
28 1 B Details Of Encumbrances Concerned To Legal.Pdf
29 1 Other – Technical.Pdf
30 2 Other – Technical.Pdf
31 3 Other – Technical.Pdf
32 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
33 1 Proforma Of Agreement For Sale.Pdf
34 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
35 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
36 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
37 Form 1.Pdf
38 Form 2.Pdf
39 Form 3.Pdf
40 Disclosure Of Sold And Booked Inventory.Pdf
41 Withdrawal Update Form 1.Pdf
43 Withdrawal Update Form 2.Pdf
45 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank FEDERAL BANK
IFSC FDRL0001755
Branch Address SHOP NO.S1,2,3 & 5, GROUND FLOOR,PRIYA MANAY APARTMENTS, KATRAP ROAD, BADLAPUR EAST,THANE
Country/City