residential Under Construction Source: rera.mh

Ashapura Bileshwar RERA Details - P51700054702, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Ashapura Bileshwar under registration P51700054702 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700054702
  • Project Name BILESHWAR
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Kalyan-Dombivali (M Corp.)
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 10,510.0
  • Total Buildings/Towers 2
  • Documents 50 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 06 February 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name ASHAPURA COMBINES

Promoters, Co-promoters & Members

NameRoleAddress
HARILAL NATHU PATELPartnerMumbai Suburban, MAHARASHTRA
VIPUL HARILAL PATELPartnerMumbai Suburban, MAHARASHTRA
MANGESH DASHRATH GAIKARPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
BILESHWAR BUILDING NO 1 23 75 19 19 19 98 NA
BILESHWAR BUILDING NO 2 23 76 19 19 19 193 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 291
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 168 units · avg area 44.10 Sq.mt.
2 BHK 96 units · avg area 58.35 Sq.mt.
Shop 27 units · avg area 14.70 Sq.mt.
  • BUILDING NO 1
  • BUILDING NO 2
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 17.94 1 0
Shop 14.41 1 0
Shop 13.31 1 0
Shop 6.87 1 0
Shop 13.06 1 0
Shop 15.7 1 0
2BHK 59.46 18 3
Shop 5.41 1 1
Shop 16.42 1 1
Shop 12.84 1 1
2BHK 57.7 18 1
1BHK 44.17 33 1
1BHK 43.23 18 0
Shop 14.99 1 0
Shop 17.7 1 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING NO 1
  • BUILDING NO 2
BUILDING NO 1 · Overall Progress 45%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work35%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

4 2 A Details Of Encumbrances Concerned To Finance.Pdf
Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 B Details Of Encumbrances Concerned To Legal.Pdf
6 2 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval NA Order For Plotted Development.Pdf
9 2 Building Plan Approval NA Order For Plotted Development.Pdf
10 1 Commencement Certificates NA Order For Plotted Development.Pdf
11 2 Commencement Certificates NA Order For Plotted Development.Pdf
12 1 Declaration About Commencement Certificate.Pdf
13 1 Declaration In FORM B.Pdf
14 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
15 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
16 1 CERSAI Details.Pdf
17 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
18 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
19 1 Proforma Of Agreement For Sale.Pdf
20 1 Proforma Of Allotment Letter.Pdf
21 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
22 1 Deviation Report With Respect To Allotment Letter.Pdf
23 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
24 1 Other – Legal.Pdf
25 2 Other – Legal.Pdf
26 3 Other – Legal.Pdf
27 4 Other – Legal.Pdf
28 5 Other – Legal.Pdf
29 1 Other – Technical.Pdf
31 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
32 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
33 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
35 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
36 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
37 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
39 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
40 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
41 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
42 1 Disclosure Of Sold Booked Inventory.Pdf
43 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
48 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
49 Form 1.Pdf
50 Form 2.Pdf
51 Form 3.Pdf
52 Disclosure Of Sold And Booked Inventory.Pdf
65 Form 2A (FY 2024 2025).Pdf
66 Form 2A (FY 2025 2026).Pdf
67 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank THE SHAMRAO VITHAL COOPERATIVE BANK
IFSC SVCB0000018
Branch Address Jayant Arcade Junction of M G Rd and Rajawadi Naka Ghatkopar East Mumbai
Country/City