residential Under Construction Source: rera.mh

Gopal Gaondevi Crown RERA Details - P51700031502, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Gopal Gaondevi Crown under registration P51700031502 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700031502
  • Project Name Gaondevi Crown
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Tisgaon
  • Original Completion 31 March 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 2,600.0
  • Total Buildings/Towers 1
  • Documents 64 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 October 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name GOPAL KRISHNA DEVELOPERS
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
RADHE KRISHNA PARKHAJI MALANG ROAD8364.31CompletedIndustrial111962004-04-212004-04-21NoNA
GOPAL KRISHNA PARK PHASE I100 FT ROAD TISGAON KALYAN EAST3506CompletedIndustrial41962004-12-272004-12-31NoNA
GOPAL KRISHNA PARK PHASE IIHAJI MALANG ROAD KALYAN EAST6672.27CompletedIndustrial4832007-06-152008-07-15NoNA
KRISHNA HEIGHT 100FT ROAD TISGAON KALYAN EAST7110CompletedIndustrial51542016-01-012016-05-30NoNA
KRISHNA PARADISE PHASE I100 FT ROAD TISGAON KALYAN EAST20107CompletedIndustrial62362016-05-042017-07-04NoNA

Promoters, Co-promoters & Members

NameRoleAddress
SURESH SITARAM SONAWANEPartnerThane, MAHARASHTRA
ASHISH SURESH SONAWANEPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Gaondevi Crown Gaondevi Crown 0 20 23 Stilt+1st To 21st Floor 22 168 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 168
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 84 units · avg area 36.88 Sq.mt.
2 BHK 84 units · avg area 51.16 Sq.mt.
  • Gaondevi Crown
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 35.81 42 42
1BHK 37.95 42 32
2BHK 50.13 42 26
2BHK 52.18 42 18
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 75.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 60.0%
Storm Water Drains % not reported Landscaping & Tree Planting 10.0% Street Lighting 50.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 80.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Gaondevi Crown
Gaondevi Crown · Overall Progress 68%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work70%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work20%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 Copy Of The Legal Title Report.Pdf
2 2 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 2 Details Of Encumbrances.Pdf
5 3 Details Of Encumbrances.Pdf
6 1 Copy Of Layout Approval (In Case Of Layout).Pdf
7 2 Copy Of Layout Approval (In Case Of Layout).Pdf
8 3 Copy Of Layout Approval (In Case Of Layout).Pdf
9 4 Copy Of Layout Approval (In Case Of Layout).Pdf
10 5 Copy Of Layout Approval (In Case Of Layout).Pdf
11 1 Building Plan Approval NA Order For Plotted Development.Pdf
12 1 Commencement Certificates NA Order For Plotted Development.Pdf
13 2 Commencement Certificates NA Order For Plotted Development.Pdf
14 3 Commencement Certificates NA Order For Plotted Development.Pdf
15 4 Commencement Certificates NA Order For Plotted Development.Pdf
16 5 Commencement Certificates NA Order For Plotted Development.Pdf
17 1 Declaration About Commencement Certificate.Pdf
18 2 Declaration About Commencement Certificate.Pdf
19 3 Declaration About Commencement Certificate.Pdf
20 1 Declaration In FORM B.Pdf
21 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
22 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
23 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
24 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
25 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
26 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
27 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
28 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
29 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
30 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
31 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
32 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
33 6 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
34 7 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
35 8 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
36 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
37 2 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
38 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
39 1 Disclosure Of Sold Booked Inventory.Pdf
40 2 Disclosure Of Sold Booked Inventory.Pdf
41 3 Disclosure Of Sold Booked Inventory.Pdf
42 4 Disclosure Of Sold Booked Inventory.Pdf
43 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
44 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
45 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
46 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
47 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
48 6 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
49 7 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
50 8 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
51 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
52 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
53 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
54 1 Proforma Of Allotment Letter.Pdf
55 2 Proforma Of Allotment Letter.Pdf
56 1 Proforma Of Agreement For Sale.Pdf
57 1 Other – Technical.Pdf
64 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
68 Withdrawal Update Form 1.Pdf
72 Withdrawal Update Form 2.Pdf
76 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000194
Branch Address Kalyan W