residential Ready to Move Source: rera.mh

Goranath Vasind Lifestyle RERA Details - P51700015907, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Goranath Vasind Lifestyle under registration P51700015907 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700015907
  • Project Name VASIND LIFESTYLE
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Shahapur
  • Village Khativali
  • Original Completion 30 December 2024
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 3,700.0
  • Total Buildings/Towers 3
  • Documents 48 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 April 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name GORANATH ESTATE PRIVATE LIMITED

Promoters, Co-promoters & Members

NameRoleAddress
JAMNA LAL DEPURADirectorMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
VASIND LIFESTYLE VL1 0 0 5 0 0 NA
VASIND LIFESTYLE VL2 0 0 5 0 0 NA
VASIND LIFESTYLE VL3 0 0 5 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 108
Configurations 10
Inventory Type RESIDENTIAL
Configuration Distribution
1 3 units · avg area 23.88 Sq.mt.
2 6 units · avg area 29.66 Sq.mt.
3 15 units · avg area 31.03 Sq.mt.
4 20 units · avg area 33.84 Sq.mt.
5 16 units · avg area 31.23 Sq.mt.
6 24 units · avg area 34.69 Sq.mt.
7 12 units · avg area 33.41 Sq.mt.
8 8 units · avg area 35.65 Sq.mt.
9 2 units · avg area 35.22 Sq.mt.
10 2 units · avg area 35.70 Sq.mt.
  • VL1
  • VL2
  • VL3
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1 20.65 1 0
5 30.28 8 0
6 33.65 8 0
4 33.67 8 0
3 30.96 8 0
2 29.24 3 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • VL1
  • VL2
  • VL3
VL1 · Overall Progress 0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 1 Declaration In FORM B.Pdf
8 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
9 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
10 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
14 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
15 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
16 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
17 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
18 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
19 1 Disclosure Of Sold Booked Inventory.Pdf
20 2 Disclosure Of Sold Booked Inventory.Pdf
21 3 Disclosure Of Sold Booked Inventory.Pdf
22 1 Certificates Of CA (Form 3).Pdf
23 2 Certificates Of CA (Form 3).Pdf
24 3 Certificates Of CA (Form 3).Pdf
25 4 Certificates Of CA (Form 3).Pdf
26 5 Certificates Of CA (Form 3).Pdf
27 6 Certificates Of CA (Form 3).Pdf
28 7 Certificates Of CA (Form 3).Pdf
29 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
30 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
31 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
32 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
33 1 Proforma Of Allotment Letter.Pdf
34 2 Proforma Of Allotment Letter.Pdf
35 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
36 1 Status Of Formation Of Legal Entity.Pdf
37 1 Status Of Conveyance.Pdf
38 2 Status Of Conveyance.Pdf
39 3 Status Of Conveyance.Pdf
40 4 Status Of Conveyance.Pdf
41 5 Status Of Conveyance.Pdf
50 6 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
51 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
58 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
59 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0001201
Branch Address ICICI BANK LTD SHOP NO 17 AND 18 REGAL INDUSTRIES COMMERCIAL BUILDING A D MARG SEWRI MUMBAI 400015 M
Country/City