Jigar Venus CHS RERA Details - P51700003962, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Jigar Venus CHS under registration P51700003962 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700003962
  • Project Name JIGAR CONSTRUCTION VENUS
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Chikanghar
  • Original Completion 31 March 2019
  • Revised Completion 30 June 2024
  • Project Area (in Sq.mt.) 2,300.0
  • Total Buildings/Towers 1
  • Documents 33 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 07 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2019 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
JIGAR CONSTRUCTION VENUS VENUS 2 23 13 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 82
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 57 units · avg area 33.12 Sq.mt.
1 RK 2 units · avg area 24.83 Sq.mt.
1 RK AND TERRACE 2 units · avg area 24.83 Sq.mt.
2 BHK 21 units · avg area 51.23 Sq.mt.
  • VENUS
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1 BHK 33.01 40 39
1 RK 24.83 2 2
1 BHK 32.82 16 16
2BHK 51.23 21 21
1 BHK 42.17 1 1
1 RK AND TERRACE 24.83 2 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • VENUS
VENUS · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 2 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration About Commencement Certificate.Pdf
9 2 Declaration About Commencement Certificate.Pdf
10 1 Declaration In FORM B.Pdf
11 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
12 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
13 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
14 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
15 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
16 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
17 1 CERSAI Details.Pdf
18 1 Disclosure Of Sold Booked Inventory.Pdf
19 1 Certificates Of CA (Form 3).Pdf
20 2 Certificates Of CA (Form 3).Pdf
21 1 Certificates Of CA (Form 5).Pdf
22 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
23 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
24 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
25 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
26 1 Proforma Of Allotment Letter.Pdf
27 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
28 1 Certificates Of Architect (Form 4).Pdf
29 1 Other.Pdf
30 2 Other.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF MAHARASHTRA
IFSC MAHB0001298
Branch Address GROUND FLOOR VARSHA PARK KHADAKPADA KALYAN WEST 421301