RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700052389
  • Project Name Upper Thane-Tiara H
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Bhiwandi
  • Village Mankoli
  • Original Completion 31 July 2027
  • Revised Completion 31 July 2027
  • Project Area (in Sq.mt.) 3,552.0
  • Total Buildings/Towers 1
  • Documents 58 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 21 August 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 July 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 July 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name LODHA DEVELOPERS LIMITED

Promoters, Co-promoters & Members

NameRoleAddress
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA
RAJENDRA LODHAChairpersonMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Upper Thane-Tiara H Wing H of Sector A Cluster 1 Point03 E 0 67 24 24 24 96 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 96
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 11 units · avg area 65.98 Sq.mt.
3 BHK 85 units · avg area 80.87 Sq.mt.
  • Wing H of Sector A Cluster 1 Point03 E
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3BHK 79.52 20 20
2BHK 63.87 4 0
2BHK 63.82 1 1
3BHK 81.29 65 0
2BHK 67.74 6 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 70.0% Water Supply 85.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 85.0%
Storm Water Drains 60.0% Landscaping & Tree Planting 40.0% Street Lighting 40.0%
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water 70.0% Solid Waste Management And Disposal 65.0%
Water Conservation /Rain Water Harvesting 65.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 60.0%
Electrical Meter Room, Sub-station, Receiving Station 60.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 60.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Wing H of Sector A Cluster 1 Point03 E
Wing H of Sector A Cluster 1 Point03 E · Overall Progress 28%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
In Progress
% Work8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 B Details Of Encumbrances Concerned To Legal.Pdf
6 2 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 2 Copy Of Layout Approval (In Case Of Layout).Pdf
9 3 Copy Of Layout Approval (In Case Of Layout).Pdf
10 4 Copy Of Layout Approval (In Case Of Layout).Pdf
11 1 Building Plan Approval NA Order For Plotted Development.Pdf
12 2 Building Plan Approval NA Order For Plotted Development.Pdf
13 3 Building Plan Approval NA Order For Plotted Development.Pdf
14 1 Commencement Certificates NA Order For Plotted Development.Pdf
15 1 Declaration About Commencement Certificate.Pdf
16 1 Declaration In FORM B.Pdf
17 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
18 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
19 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
20 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
21 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
22 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
23 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
24 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
25 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
26 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
27 1 CERSAI Details.Pdf
28 2 CERSAI Details.Pdf
29 1 Disclosure Of Sold Booked Inventory.Pdf
30 2 Disclosure Of Sold Booked Inventory.Pdf
31 3 Disclosure Of Sold Booked Inventory.Pdf
32 4 Disclosure Of Sold Booked Inventory.Pdf
33 5 Disclosure Of Sold Booked Inventory.Pdf
34 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
35 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
36 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
37 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
38 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
39 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
40 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
41 1 Proforma Of Agreement For Sale.Pdf
42 1 Proforma Of Allotment Letter.Pdf
43 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
44 1 Deviation Report With Respect To Allotment Letter.Pdf
45 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
46 1 Other – Legal.Pdf
47 2 Other – Legal.Pdf
48 3 Other – Legal.Pdf
59 Form 1.Pdf
60 Form 2.Pdf
61 Form 3.Pdf
62 Disclosure Of Sold And Booked Inventory.Pdf
67 Self Declaration Of Quarterly Progress.Pdf
68 Others.Pdf
81 Form 2A (FY 2024 2025).Pdf
82 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000323
Branch Address Bombay Hub, Z Wing, Kamala Mills Compound,Senapati Bapat Marg, Lower Parel, Mumbai 400013
Country/City