Marathon Nagari NX RERA Details - P51700005049, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Marathon Nagari NX under registration P51700005049 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700005049
  • Project Name MARATHON NAGARI NX VITORIA D
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 31 December 2019
  • Revised Completion 30 December 2021
  • Project Area (in Sq.mt.) 194.0
  • Total Buildings/Towers 1
  • Documents 65 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2019 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2021 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name MARATHON REALTY PVT LTD
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
MARATHON NAGARI PHASE 1SHIRGAON BADLAPUR EAST34277CompletedResidential / Group Housing326962012-07-312013-02-26NoNA

Promoters, Co-promoters & Members

NameRoleAddress
CHETAN RAMNIKLAL SHAHDirectorMumbai Suburban, MAHARASHTRA
MAYUR RAMNIKLAL SHAHDirectorMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
MARATHON NAGARI NX VITORIA D MARATHON NAGARI NX VITORIA D 0 1 8 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 24
Configurations 8
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 11 units · avg area 33.66 Sq.mt.
2 BHK 7 units · avg area 59.42 Sq.mt.
S 019 1 unit · avg area 9.21 Sq.mt.
S 020 1 unit · avg area 13.03 Sq.mt.
S 021 1 unit · avg area 11.01 Sq.mt.
S 022 1 unit · avg area 12.81 Sq.mt.
S 023 1 unit · avg area 9.92 Sq.mt.
S 024 1 unit · avg area 8.92 Sq.mt.
  • MARATHON NAGARI NX VITORIA D
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 34.98 7 7
1BHK 31.34 4 4
S 024 8.92 1 0
2BHK 59.42 7 7
S 023 9.92 1 0
S 022 12.81 1 0
S 021 11.01 1 0
S 019 9.21 1 0
S 020 13.03 1 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • MARATHON NAGARI NX VITORIA D
MARATHON NAGARI NX VITORIA D · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

33 3 Certificates Of CA (Form 5).Pdf
Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 2 Copy Of Layout Approval (In Case Of Layout).Pdf
6 3 Copy Of Layout Approval (In Case Of Layout).Pdf
7 4 Copy Of Layout Approval (In Case Of Layout).Pdf
8 5 Copy Of Layout Approval (In Case Of Layout).Pdf
9 6 Copy Of Layout Approval (In Case Of Layout).Pdf
10 7 Copy Of Layout Approval (In Case Of Layout).Pdf
11 1 Building Plan Approval (IOD).Pdf
12 1 Commencement Certificates NA Order For Plotted Development.Pdf
13 1 Declaration In FORM B.Pdf
14 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
15 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
16 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
17 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
18 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
19 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
20 5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
21 6 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
22 7 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
23 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
24 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
25 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
26 1 Certificates Of CA (Form 3).Pdf
27 2 Certificates Of CA (Form 3).Pdf
28 3 Certificates Of CA (Form 3).Pdf
29 4 Certificates Of CA (Form 3).Pdf
30 5 Certificates Of CA (Form 3).Pdf
31 1 Certificates Of CA (Form 5).Pdf
32 2 Certificates Of CA (Form 5).Pdf
34 1 Proforma Of Allotment Letter.Pdf
35 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
36 1 Other.Pdf
39 12 Certificates Of CA (Form 3).Pdf
40 11 Certificates Of CA (Form 3).Pdf
41 10 Certificates Of CA (Form 3).Pdf
42 9 Certificates Of CA (Form 3).Pdf
43 8 Certificates Of CA (Form 3).Pdf
44 7 Certificates Of CA (Form 3).Pdf
45 6 Certificates Of CA (Form 3).Pdf
49 12 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
50 11 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
51 10 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
52 9 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
53 5 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
54 8 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
55 7 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
56 6 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
57 4 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
58 3 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
59 2 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
61 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
62 2 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
63 3 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
64 4 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
66 2 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
67 3 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
68 4 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
69 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank INDUSIND BANK
IFSC INDB0000047
Branch Address MARATHON MAX SHOP NO 12 TO 15 MULUND GOREGAON LINK ROAD MULUND WEST MUMBAI 400080