Om Sadguru Darshan RERA Details - P51700017137, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Om Sadguru Darshan under registration P51700017137 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700017137
  • Project Name Sadguru Darshan
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Murbad
  • Village Murbad
  • Original Completion 30 May 2025
  • Revised Completion 29 May 2028
  • Project Area (in Sq.mt.) 4,340.0
  • Total Buildings/Towers 3
  • Documents 45 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 16 July 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 May 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 29 May 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name OM SADGURU REALTORS

Promoters, Co-promoters & Members

NameRoleAddress
SHIVKUMAR RAMMILAN MISHRAPartnerThane, MAHARASHTRA
KOKILA VASANTRAO CHAUDHARIPartnerThane, MAHARASHTRA
SANGITA VIRENDRASINGH CHAUDHARIPartnerThane, MAHARASHTRA
SUSHILA RAMMILAN MISHRAPartnerThane, MAHARASHTRA
SAGAR RAMMILAN MISHRAPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Sadguru Darshan Building 1 88 3 6 0 6 49 NA
Sadguru Darshan BUILDING 2 104 4 6 7 6 63 NA
Sadguru Darshan BUILDING 3 96 1 6 6 6 40 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 117
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 91 units · avg area 32.04 Sq.mt.
1 RK 2 units · avg area 19.89 Sq.mt.
2 BHK 24 units · avg area 40.45 Sq.mt.
  • Building 1
  • BUILDING 2
  • BUILDING 3
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1 BHK 30.63 2 0
2 BHK 42.28 2 0
1 BHK 29.7 2 0
1 RK 20.29 1 0
2 BHK 38.61 2 0
2 BHK 41.88 2 0
2 BHK 37.94 2 0
1 BHK 31.89 1 0
1 BHK 31.88 4 0
1 BHK 34.48 4 0
1 BHK 30.21 1 0
1 BHK 31.39 1 0
1 BHK 30.99 2 0
1BHK 35.47 2 0
1 BHK 33.98 2 0
1 BHK 33.34 2 0
1 BHK 34.83 2 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Building 1
  • BUILDING 2
  • BUILDING 3
Building 1 · Overall Progress 28%
Stilt Floor
Not Started
% Work0%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work12.5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

188 Form 5 (FY 2021 2022).Pdf
Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 2 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration In FORM B.Pdf
9 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
10 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
11 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
12 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
13 1 Certificates Of CA (Form 3).Pdf
14 2 Certificates Of CA (Form 3).Pdf
15 1 Proforma Of Allotment Letter.Pdf
16 2 Proforma Of Allotment Letter.Pdf
19 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
22 3 Certificates Of CA (Form 3).Pdf
25 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
29 4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
33 4 Certificates Of CA (Form 3).Pdf
37 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
38 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
39 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
40 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
65 5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
78 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
79 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
80 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
94 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
95 Form 1.Pdf
96 Form 2.Pdf
97 Form 3.Pdf
176 Withdrawal Update Form 1.Pdf
179 Withdrawal Update Form 2.Pdf
182 Withdrawal Update Form 3.Pdf
185 Form 5 (FY 2018 2019).Pdf
186 Form 5 (FY 2019 2020).Pdf
187 Form 5 (FY 2020 2021).Pdf
189 Form 5 (FY 2022 2023).Pdf
190 Form 5 (FY 2023 2024).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0001495
Branch Address MURBAD,THANE-421401
Country/City