  • RERA Number P51700010840
  • Project Name GARDEN CITY
  • Project Type Residential
  • Project Status Under Construction
  • State MAHARASHTRA
  • District Thane
  • Taluka Bhiwandi
  • Village Bhiwandi (M Corp.)
  • Original Completion 31 December 2027
  • Revised Completion 30 December 2028
  • Project Area (in Sq.mt.) 9,674.00
  • Total Buildings/Towers 5
  • Documents 16 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 31 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Pakshal Builders and Developers
Other Description NA

Promoters, Co-promoters & Members

NameRole
Pallavi Prakash WaghPartner
PARAG PRAKASH WAGH HUF KARTA PARAG PRAKASH WAGHPartner
Parag Prakash WaghAuthorized Signatory
VAIJAYANTI PARAG WAGHPartner
Mulbai Hirji BhanushaliPartner
Vasant Nanji Bhanushali Karta Vasant Nanji BhanushaliPartner
Dinesh Nanji Bhanushali HUF Karta Dinesh Nanji BhanushaliPartner
Deepakkumar Hirji BhanushaliPartner
Naresh Hirji BhanushaliAuthorized Signatory
Chaganlal Narayanji PadhiarPartner
Chaganlal Narayanji Padhiar HUF Karta Chaganlal Narayanji PadhiarPartner
Hitesh Chaganlal PadhiarAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
GARDEN CITY LOTUS BUILDING NO2 2020-12-31 0 1 0 8 1 0 7
GARDEN CITY Building Number 1 - 0 0 0 0 0 0 0
GARDEN CITY Building Number 3 - 0 0 0 0 0 0 0
GARDEN CITY Building Number 5 - 0 0 0 0 0 0 0
GARDEN CITY Building Number 4 - 0 0 0 0 0 0 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 168
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 128 units · avg area 35.28 Sq.mt.
1 RK 3 units · avg area 22.00 Sq.mt.
2 BHK 37 units · avg area 46.00 Sq.mt.
  • LOTUS BUILDING NO2
  • Building Number 1
  • Building Number 3
  • Building Number 5
  • Building Number 4
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 46.00 13 11
1BHK 36.00 28 23
1BHK 34.00 12 9
1BHK 35.00 3 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 7 5 90
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting % not reported Energy Management % not reported
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply % not reported Sewerage % not reported
Storm Water Drains % not reported Landscaping Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • LOTUS BUILDING NO2
  • Building Number 1
  • Building Number 3
  • Building Number 5
  • Building Number 4
LOTUS BUILDING NO2 · Overall Progress 45%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
In Progress
% Work90%
X number of Slabs of Super Structure
In Progress
% Work80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Not Started
% Work0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work80%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Certificates Of CA (Form 5)
2 Certificates Of CA (Form 5)
3 Certificates Of CA (Form 5)
1 Proforma Of Allotment Letter
1 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank CSB Bank
IFSC CSKB0000302
Country/City