Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Sai Satyam Residency Kalyan West RERA Details - P51700015767, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sai Satyam Residency Kalyan West under registration P51700015767 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700015767
  • Project Name SAI SATYAM RESIDENCY
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Kalyan
  • Original Completion 30 December 2023
  • Revised Completion 30 December 2023
  • Project Area (in Sq.mt.) 6,080.0
  • Total Buildings/Towers 4
  • Documents 43 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 26 March 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SAI SATYAM GROUP
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
SAI SATYAM RESIDENCY - WING E TO WING I SN 65 HN 7 PART 2 AT WADEGHAR NEAR DON BOSCO SCHOOL KALYAN - WEST6080CompletedResidential / Group Housing51372016-05-292017-04-29NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SAI SATYAM RESIDENCY Cancelled 0 0 0 0 0 NA
SAI SATYAM RESIDENCY WING C 0 6 12 0 0 NA
SAI SATYAM RESIDENCY WING D 0 6 12 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 80
Configurations 6
Inventory Type RESIDENTIAL
Configuration Distribution
2RK TYPE3 4 units · avg area 39.18 Sq.mt.
2RK TYPE1 20 units · avg area 33.33 Sq.mt.
2RK TYPE2 20 units · avg area 33.43 Sq.mt.
3RK TYPE1 36 units · avg area 44.91 Sq.mt.
none 0 units
Cancelled 0 units
  • Cancelled
  • WING C
  • WING D
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
none 0.0 0 0
Cancelled 0.0 0 0
none 0.0 0 0
Cancelled 0.0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Cancelled
  • WING C
  • WING D
Cancelled · Overall Progress 0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 Copy Of The Legal Title Report.Pdf
2 1 Details Of Encumbrances.Pdf
3 1 Copy Of Layout Approval (In Case Of Layout).Pdf
4 2 Copy Of Layout Approval (In Case Of Layout).Pdf
5 3 Copy Of Layout Approval (In Case Of Layout).Pdf
6 4 Copy Of Layout Approval (In Case Of Layout).Pdf
7 5 Copy Of Layout Approval (In Case Of Layout).Pdf
8 6 Copy Of Layout Approval (In Case Of Layout).Pdf
9 7 Copy Of Layout Approval (In Case Of Layout).Pdf
10 8 Copy Of Layout Approval (In Case Of Layout).Pdf
11 9 Copy Of Layout Approval (In Case Of Layout).Pdf
12 10 Copy Of Layout Approval (In Case Of Layout).Pdf
13 11 Copy Of Layout Approval (In Case Of Layout).Pdf
14 12 Copy Of Layout Approval (In Case Of Layout).Pdf
15 13 Copy Of Layout Approval (In Case Of Layout).Pdf
16 14 Copy Of Layout Approval (In Case Of Layout).Pdf
17 15 Copy Of Layout Approval (In Case Of Layout).Pdf
18 16 Copy Of Layout Approval (In Case Of Layout).Pdf
19 17 Copy Of Layout Approval (In Case Of Layout).Pdf
20 18 Copy Of Layout Approval (In Case Of Layout).Pdf
21 19 Copy Of Layout Approval (In Case Of Layout).Pdf
22 20 Copy Of Layout Approval (In Case Of Layout).Pdf
23 1 Building Plan Approval (IOD).Pdf
24 1 Commencement Certificates NA Order For Plotted Development.Pdf
25 2 Commencement Certificates NA Order For Plotted Development.Pdf
26 1 Declaration In FORM B.Pdf
27 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
28 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
29 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
30 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
31 2 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
32 3 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
33 4 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
34 1 Disclosure Of Sold Booked Inventory.Pdf
35 2 Disclosure Of Sold Booked Inventory.Pdf
36 1 Certificates Of CA (Form 3).Pdf
37 2 Certificates Of CA (Form 3).Pdf
38 1 Proforma Of Allotment Letter.Pdf
39 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
40 2 Architect’S Certificate On Completion Of Project (Form 4).Pdf
41 1 Other.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank G P PARSIK BANK
IFSC PJSB0000021
Branch Address PYARA-DECK BLDG GALA NO 5 AND 6 OPP BIRLA COLLEGE KALYAN -WEST
Country/City