Samarth Sai Seasons Sahara RERA Details - P51700025218, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Samarth Sai Seasons Sahara under registration P51700025218 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700025218
  • Project Name SEASONS SAHARA BUILDING NO 2
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village PISAVALI
  • Original Completion 30 December 2024
  • Revised Completion 30 December 2024
  • Project Area (in Sq.mt.) 3,350.0
  • Total Buildings/Towers 1
  • Documents 61 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 23 March 2020 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SAMARTH SAI BUILDERS & DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
HITESH JAIRAM NIHALANIPartnerThane, MAHARASHTRA
DINESH RAMDAS MHATREPartnerThane, MAHARASHTRA
PURAN NAMOMAL KUKREJAPartnerThane, MAHARASHTRA
RAJESH CHANDERLAL METHWANIPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SEASONS SAHARA BUILDING NO 2 SEASONS SAHARA BUILDING NO 2 0 14 17 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 120
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 60 units · avg area 32.05 Sq.mt.
2 BHK 60 units · avg area 46.27 Sq.mt.
  • SEASONS SAHARA BUILDING NO 2
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 47.27 30 30
1BHK 30.64 30 29
2BHK 45.27 30 30
1BHK 33.45 30 30
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SEASONS SAHARA BUILDING NO 2
SEASONS SAHARA BUILDING NO 2 · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
1 1 PAN Card.Pdf
Mh Certificate Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 2 Copy Of Layout Approval (In Case Of Layout).Pdf
6 3 Copy Of Layout Approval (In Case Of Layout).Pdf
7 4 Copy Of Layout Approval (In Case Of Layout).Pdf
8 5 Copy Of Layout Approval (In Case Of Layout).Pdf
9 6 Copy Of Layout Approval (In Case Of Layout).Pdf
10 1 Building Plan Approval NA Order For Plotted Development.Pdf
11 1 Commencement Certificates NA Order For Plotted Development.Pdf
12 2 Commencement Certificates NA Order For Plotted Development.Pdf
13 1 Declaration About Commencement Certificate.Pdf
14 1 Declaration In FORM B.Pdf
15 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
16 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
17 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
18 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
19 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
20 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
21 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
22 8 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
23 9 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
24 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
25 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
26 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
27 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
28 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
29 6 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
30 7 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
31 8 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
32 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
33 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
34 2 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
35 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
36 1 Disclosure Of Sold Booked Inventory.Pdf
37 2 Disclosure Of Sold Booked Inventory.Pdf
38 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
39 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
40 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
41 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
42 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
43 6 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
44 7 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
45 8 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
46 9 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
47 10 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
48 11 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
49 12 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
50 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
51 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
52 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
53 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
54 1 Proforma Of Allotment Letter.Pdf
55 1 Details Of Restarting Of Construction Work Post Lockdown.Pdf
56 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
57 2 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
58 3 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
59 10 Architect’S Certificate On Completion Of Project (Form 4).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0001153
Branch Address KHADAKPADA KALYAN 421301
Country/City