Sanidhya Mata Ramai Palace RERA Details - P51700018287, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sanidhya Mata Ramai Palace under registration P51700018287 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700018287
  • Project Name MATA RAMAI PALACE
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 30 December 2022
  • Revised Completion 30 December 2023
  • Project Area (in Sq.mt.) 2,070.0
  • Total Buildings/Towers 1
  • Documents 45 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 22 October 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2022 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Sanidhya Enterprises

Promoters, Co-promoters & Members

NameRoleAddress
Vishwadeep Jaywant GaikwadPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
MATA RAMAI PALACE MATA RAMAI PALACE 54 0 6 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 58
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 4 units · avg area 20.13 Sq.mt.
1 BHK 54 units · avg area 25.34 Sq.mt.
  • MATA RAMAI PALACE
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1RK 20.13 4 3
1BHK 24.65 20 17
1BHK 25.93 18 14
1BHK 25.53 16 12
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 50.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • MATA RAMAI PALACE
MATA RAMAI PALACE · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 1 Declaration About Commencement Certificate.Pdf
8 1 Declaration In FORM B.Pdf
9 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
10 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
11 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
12 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
13 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
14 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
15 5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
16 6 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
17 7 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
18 8 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
19 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
20 2 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
21 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
22 1 Disclosure Of Sold Booked Inventory.Pdf
23 1 Certificates Of CA (Form 3).Pdf
24 2 Certificates Of CA (Form 3).Pdf
25 3 Certificates Of CA (Form 3).Pdf
26 4 Certificates Of CA (Form 3).Pdf
27 5 Certificates Of CA (Form 3).Pdf
28 6 Certificates Of CA (Form 3).Pdf
29 7 Certificates Of CA (Form 3).Pdf
30 8 Certificates Of CA (Form 3).Pdf
31 9 Certificates Of CA (Form 3).Pdf
32 10 Certificates Of CA (Form 3).Pdf
33 11 Certificates Of CA (Form 3).Pdf
34 12 Certificates Of CA (Form 3).Pdf
35 13 Certificates Of CA (Form 3).Pdf
36 14 Certificates Of CA (Form 3).Pdf
37 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
38 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
39 1 Proforma Of Allotment Letter.Pdf
40 1 Other.Pdf
41 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
42 2 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank UNION BANK OF INDIA
IFSC UBIN0556921
Branch Address DWARAKADHISH NIVAS DATTA CHOWK BELAVALI BADLAPUR WEST MAHARASHTRA
Country/City