Seasons Mayfair RERA Details - P51700054746, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Seasons Mayfair under registration P51700054746 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700054746
  • Project Name Seasons Mayfair
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Chikanghar
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 1,434.0
  • Total Buildings/Towers 1
  • Documents 41 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 12 February 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Tiruma Sai Builders

Promoters, Co-promoters & Members

NameRoleAddress
Aarush GandhiPartnerRaigarh, MAHARASHTRA
Bhavesh NihalaniPartnerThane, MAHARASHTRA
Hitesh NihalaniPartnerThane, MAHARASHTRA
Manish DulaniPartnerThane, MAHARASHTRA
Vijay BudhwaniPartnerThane, MAHARASHTRA
Vivek MadarkalPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Seasons Mayfair Seasons Mayfair 70 32 15 1st to 14 floors 14 66 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 66
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 2 units · avg area 41.63 Sq.mt.
2 BHK 40 units · avg area 52.69 Sq.mt.
3 BHK 14 units · avg area 64.54 Sq.mt.
Shop 10 units · avg area 16.21 Sq.mt.
  • Seasons Mayfair
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 41.63 2 0
Shop 12.65 1 1
Shop 13.67 1 1
Shop 16.39 1 1
3BHK 64.54 14 4
2BHK 51.88 14 6
Shop 23.16 1 1
Shop 12.71 1 0
2BHK 53.79 14 2
2BHK 52.36 12 4
Shop 20.81 1 0
Shop 11.86 1 1
Shop 16.95 3 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Seasons Mayfair
Seasons Mayfair · Overall Progress 69%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work60%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 A Details Of Encumbrances Concerned To Finance.Pdf
5 2 A Details Of Encumbrances Concerned To Finance.Pdf
6 3 A Details Of Encumbrances Concerned To Finance.Pdf
7 1 B Details Of Encumbrances Concerned To Legal.Pdf
8 2 B Details Of Encumbrances Concerned To Legal.Pdf
9 3 B Details Of Encumbrances Concerned To Legal.Pdf
10 1 Copy Of Layout Approval (In Case Of Layout).Pdf
11 1 Building Plan Approval NA Order For Plotted Development.Pdf
12 1 Commencement Certificates NA Order For Plotted Development.Pdf
13 1 Declaration About Commencement Certificate.Pdf
14 1 Declaration In FORM B.Pdf
15 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
16 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
17 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
18 1 CERSAI Details.Pdf
19 1 Disclosure Of Sold Booked Inventory.Pdf
20 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
21 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
22 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
23 1 Proforma Of Allotment Letter.Pdf
24 1 Proforma Of Agreement For Sale.Pdf
25 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
26 1 Deviation Report With Respect To Allotment Letter.Pdf
27 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
28 1 Other – Legal.Pdf
29 2 Other – Legal.Pdf
30 3 Other – Legal.Pdf
31 4 Other – Legal.Pdf
32 5 Other – Legal.Pdf
33 1 Other – Technical.Pdf
38 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
39 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
41 Withdrawal Update Form 1.Pdf
45 Withdrawal Update Form 2.Pdf
49 Withdrawal Update Form 3.Pdf
53 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0001153
Branch Address Khadakpada Kalyan