residential Partially Ready To Move Source: rera.mh

Shree Nandanvan homes RERA Details - P51700013525, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shree Nandanvan homes under registration P51700013525 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700013525
  • Project Name NANDANVAN HOMES-C1
  • Project Type Others
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 30 June 2018
  • Revised Completion 30 June 2018
  • Project Area (in Sq.mt.) 2,110.0
  • Total Buildings/Towers 1
  • Documents 27 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 October 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2018 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SHREE KRUPA BUILDERS
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
NANDANVAN HOMES A-1 A2PARSIK NAGAR KALWA THANE8252CompletedResidential / Group Housing11362015-09-302015-12-31NoNA
NANDANVAN HOMES-D1D2,D4,C1Plot bearing Gut No 86 1 CTS No 195 A Gut No 90 CTS No 56 Gut No 93 Gut No 89 CTS No 57 Gut No 101 1 101 2 Gut No 103 1 103 2 CTS No 59 104 CTS No 60 & 105 CTS No 61 at village Parsik Kalwa W Taluka & District Thane20480.16CompletedIndustrial31152017-12-182017-12-18NoNA

Promoters, Co-promoters & Members

NameRoleAddress
NANDKUMAR BALKRISHNA SALVIPartnerThane, MAHARASHTRA
SANDEEP NANDKUMAR SALVIPartnerThane, MAHARASHTRA
NILESH BALKRISHNA SALVIPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
NANDANVAN HOMES-C1 NANDANVAN HOMES C-1 15 1 16 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 5
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
OFFICE TYPE A 5 units · avg area 18.15 Sq.mt.
  • NANDANVAN HOMES C-1
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
OFFICE TYPE A 18.15 5 5
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • NANDANVAN HOMES C-1
NANDANVAN HOMES C-1 · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 3 Copy Of The Legal Title Report.Pdf
5 1 Details Of Encumbrances.Pdf
6 1 Copy Of Layout Approval (In Case Of Layout).Pdf
7 2 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval (IOD).Pdf
9 2 Building Plan Approval (IOD).Pdf
10 1 Commencement Certificates NA Order For Plotted Development.Pdf
11 1 Declaration In FORM B.Pdf
12 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
13 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
14 1 Certificates Of CA (Form 3).Pdf
15 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2017 18).Pdf
16 1 Proforma Of Allotment Letter.Pdf
17 2 Proforma Of Allotment Letter.Pdf
18 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
19 2 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
20 2 Architect’S Certificate On Completion Of Project (Form 4).Pdf
21 1 Status Of Formation Of Legal Entity (Society Co Op Etc.).Pdf
22 1 Other.Pdf
23 2 Other.Pdf
24 3 Other.Pdf
25 4 Other.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0001803
Branch Address KALWA, THANE WEST
Country/City