residential Under Construction Source: rera.mh

Soman Shrishti RERA Details - P51700076619, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Soman Shrishti under registration P51700076619 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700076619
  • Project Name Soman Shrishti Villa
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Ambarnath(M Cl)
  • Original Completion 31 December 2029
  • Revised Completion 31 December 2029
  • Project Area (in Sq.mt.) 2,220.48
  • Total Buildings/Towers 2
  • Documents 46 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 18 June 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2029 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2029 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Soman Sons Nirmaan LLP

Promoters, Co-promoters & Members

NameRoleAddress
Anup Madathingal SomanPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Soman Shrishti Villa C1 Building 0 12 3 3 3 3 NA
Soman Shrishti Villa D1 Building 0 20 3 3 3 5 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 8
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
Villas 3 units · avg area 285.78 Sq.mt.
Villa 5 units · avg area 225.17 Sq.mt.
  • C1 Building
  • D1 Building
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Villas 285.78 3 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • C1 Building
  • D1 Building
C1 Building · Overall Progress 30%
Excavation
In Progress
% Work65%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
In Progress
% Work65%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
In Progress
% Work65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work45%
Sanitary Fittings within the flats / premises
In Progress
% Work25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 B Details Of Encumbrances Concerned To Legal.Pdf
6 2 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval NA Order For Plotted Development.Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 1 Declaration About Commencement Certificate.Pdf
11 1 Declaration In FORM B.Pdf
12 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 CERSAI Details.Pdf
14 1 Disclosure Of Sold Booked Inventory.Pdf
15 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
16 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
17 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
18 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
19 1 Proforma Of Agreement For Sale.Pdf
20 1 Proforma Of Allotment Letter.Pdf
21 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
22 1 Deviation Report With Respect To Allotment Letter.Pdf
23 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
24 1 Other – Technical.Pdf
25 2 Other – Technical.Pdf
26 3 Other – Technical.Pdf
27 4 Other – Technical.Pdf
29 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
32 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
33 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
34 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
36 2 Disclosure Of Sold Booked Inventory.Pdf
37 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
38 2 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
39 3 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
45 Form 1.Pdf
46 Form 2.Pdf
47 Form 3.Pdf
48 Disclosure Of Sold And Booked Inventory.Pdf
49 Others.Pdf
70 Withdrawal Update Form 1.Pdf
74 Withdrawal Update Form 2.Pdf
78 Withdrawal Update Form 3.Pdf
82 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
IFSC SBIN0012521
Branch Address Kohinoor Industrial Area First Floor Goregaon East Mombai
Country/City