Swaminarayan City RERA Details - P51700031749, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Swaminarayan City under registration P51700031749 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700031749
  • Project Name Swaminarayan City Phase 1B
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village DOMBIVLI
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 1,600.0
  • Total Buildings/Towers 1
  • Documents 76 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 November 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Swaminarayan Life Space LLP

Promoters, Co-promoters & Members

NameRoleAddress
Pundalik Balu MhatrePartnerThane, MAHARASHTRA
Jayesh Pundlik MhatrePartnerThane, MAHARASHTRA
Dipesh Pundlik MhatrePartnerThane, MAHARASHTRA
Dharmesh Ashok JoshiPartnerThane, MAHARASHTRA
Vishal Ashok JoshiPartnerThane, MAHARASHTRA
Rasiklal Doongershi NisarPartnerThane, MAHARASHTRA
Hirji Laxman PatelPartnerThane, MAHARASHTRA
Sachin Mulchand VaviyaPartnerThane, MAHARASHTRA
Ashish Ramesh MansetaPartnerThane, MAHARASHTRA
Jeram Shamji PatelPartnerRaigarh, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Swaminarayan City Phase 1B GEORGIA 0 57 37 37 33 224 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • GEORGIA
GEORGIA · Overall Progress 39%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
In Progress
% Work25%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work52%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work20%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work26%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work1%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 2 Copy Of Layout Approval (In Case Of Layout).Pdf
6 3 Copy Of Layout Approval (In Case Of Layout).Pdf
7 4 Copy Of Layout Approval (In Case Of Layout).Pdf
8 5 Copy Of Layout Approval (In Case Of Layout).Pdf
9 6 Copy Of Layout Approval (In Case Of Layout).Pdf
10 7 Copy Of Layout Approval (In Case Of Layout).Pdf
11 8 Copy Of Layout Approval (In Case Of Layout).Pdf
12 9 Copy Of Layout Approval (In Case Of Layout).Pdf
13 10 Copy Of Layout Approval (In Case Of Layout).Pdf
14 11 Copy Of Layout Approval (In Case Of Layout).Pdf
15 1 Building Plan Approval NA Order For Plotted Development.Pdf
16 2 Building Plan Approval NA Order For Plotted Development.Pdf
17 3 Building Plan Approval NA Order For Plotted Development.Pdf
18 4 Building Plan Approval NA Order For Plotted Development.Pdf
19 5 Building Plan Approval NA Order For Plotted Development.Pdf
20 6 Building Plan Approval NA Order For Plotted Development.Pdf
21 7 Building Plan Approval NA Order For Plotted Development.Pdf
22 8 Building Plan Approval NA Order For Plotted Development.Pdf
23 9 Building Plan Approval NA Order For Plotted Development.Pdf
24 10 Building Plan Approval NA Order For Plotted Development.Pdf
25 11 Building Plan Approval NA Order For Plotted Development.Pdf
26 1 Commencement Certificates NA Order For Plotted Development.Pdf
27 2 Commencement Certificates NA Order For Plotted Development.Pdf
28 3 Commencement Certificates NA Order For Plotted Development.Pdf
29 1 Declaration About Commencement Certificate.Pdf
30 1 Declaration In FORM B.Pdf
31 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
32 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
33 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
34 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
35 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
36 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
37 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
38 8 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
39 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
40 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
41 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
42 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
43 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
44 6 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
45 7 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
46 8 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
47 1 Disclosure Of Sold Booked Inventory.Pdf
48 2 Disclosure Of Sold Booked Inventory.Pdf
49 3 Disclosure Of Sold Booked Inventory.Pdf
50 4 Disclosure Of Sold Booked Inventory.Pdf
51 5 Disclosure Of Sold Booked Inventory.Pdf
52 6 Disclosure Of Sold Booked Inventory.Pdf
53 7 Disclosure Of Sold Booked Inventory.Pdf
54 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
55 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
56 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
57 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
58 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
59 6 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
60 7 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
61 8 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
62 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
63 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
64 1 Proforma Of Allotment Letter.Pdf
65 2 Proforma Of Allotment Letter.Pdf
66 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
79 Form 1.Pdf
80 Form 2.Pdf
81 Form 3.Pdf
82 Disclosure Of Sold And Booked Inventory.Pdf
87 Withdrawal Update Form 1.Pdf
90 Withdrawal Update Form 2.Pdf
93 Withdrawal Update Form 3.Pdf
96 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0000669
Branch Address Tandon Road
Country/City