Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Wadhwa Rhodesia RERA Details - P51700007370, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Wadhwa Rhodesia under registration P51700007370 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700007370
  • Project Name WADHWA RHODESIA PHASE-II
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Bhiwandi
  • Village Bhiwandi (M Corp.)
  • Original Completion 30 December 2022
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 3,949.4
  • Total Buildings/Towers 1
  • Documents 46 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 17 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2022 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name WADHWA BUILDCON LLP

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
WADHWA RHODESIA PHASE-II SHIV CRYSTAL 0 0 5 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 67
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
SHOP 67 units · avg area 33.85 Sq.mt.
  • SHIV CRYSTAL
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
SHOP 71.93 1 0
SHOP 31.82 4 4
SHOP 83.31 1 1
SHOP 79.0 1 1
SHOP 35.14 2 0
SHOP 35.42 2 0
SHOP 35.54 2 0
SHOP 35.71 1 0
SHOP 76.27 1 0
SHOP 28.62 2 0
SHOP 38.38 1 0
SHOP 38.95 1 0
SHOP 41.72 1 1
SHOP 41.76 2 0
SHOP 43.98 2 0
SHOP 50.64 2 0
SHOP 46.01 2 0
SHOP 24.28 2 0
SHOP 9.38 2 0
SHOP 9.53 1 0
SHOP 10.17 2 0
SHOP 10.47 1 0
SHOP 18.15 1 0
SHOP 34.86 2 0
SHOP 127.51 1 0
SHOP 31.7 4 1
SHOP 19.37 2 0
SHOP 20.31 4 0
SHOP 23.97 10 0
SHOP 37.3 1 0
SHOP 32.98 2 0
SHOP 32.93 2 0
SHOP 31.2 2 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SHIV CRYSTAL
SHIV CRYSTAL · Overall Progress 5%
Excavation
In Progress
% Work50%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 Copy Of The Legal Title Report.Pdf
2 1 Details Of Encumbrances.Pdf
3 1 Copy Of Layout Approval (In Case Of Layout).Pdf
4 1 Building Plan Approval (IOD).Pdf
5 1 Commencement Certificates NA Order For Plotted Development.Pdf
6 1 Declaration About Commencement Certificate.Pdf
7 1 Declaration In FORM B.Pdf
8 2 Declaration In FORM B.Pdf
9 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
10 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
11 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
12 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
13 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
14 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
15 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
16 5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
17 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
18 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
19 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
20 1 Disclosure Of Sold Booked Inventory.Pdf
21 2 Disclosure Of Sold Booked Inventory.Pdf
22 1 Certificates Of CA (Form 3).Pdf
23 2 Certificates Of CA (Form 3).Pdf
24 3 Certificates Of CA (Form 3).Pdf
25 4 Certificates Of CA (Form 3).Pdf
26 5 Certificates Of CA (Form 3).Pdf
27 6 Certificates Of CA (Form 3).Pdf
28 7 Certificates Of CA (Form 3).Pdf
29 8 Certificates Of CA (Form 3).Pdf
30 9 Certificates Of CA (Form 3).Pdf
31 10 Certificates Of CA (Form 3).Pdf
32 11 Certificates Of CA (Form 3).Pdf
33 12 Certificates Of CA (Form 3).Pdf
34 13 Certificates Of CA (Form 3).Pdf
35 14 Certificates Of CA (Form 3).Pdf
36 1 Certificates Of CA (Form 5).Pdf
37 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
38 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
39 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
40 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
41 2 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
42 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
43 1 Proforma Of Allotment Letter.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF INDIA
IFSC BKID0000068
Branch Address BANK OF INDIA PANCHPAKHADI THANE WEST
Country/City