- RERA Number UPRERAPRJ230024
- Project Name LAXMI VILLAS
- Project Type Residential
- Project Status Under Construction
- State Uttar Pradesh
- District Ghaziabad
- Taluka Select
- Authority Ghaziabad Development Authority
- Original Completion 27 March 2027
- Revised Completion 27 March 2027
- Project Area (in Sq.mt.) 10,721
- Documents 69 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Primary Promoter
ASCENT DEVELOPWELL PVT.LTD CompanyLand, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Land Type Khasra | Plot No. 1226 |
| Land Area (in Sq.mt.) 9,720 | |
| Land Type Khasra | Plot No. 1227 |
| Land Area (in Sq.mt.) 1,888 |
RERA Coordinates |
|
| Latitude, Longitude 28.708766, 77.433413 | |
Plans & Approvals
Statutory approvals obtained or pending against the project site.
| Permit Number | Plotting Resi development/Plotted Housing/01324/GDA/LD/20-21/0675/15052021 |
|---|---|
| Permit Date | 28 March 2022 |
| Valid Upto | 27 March 2027 |
| Extendable Upto | 27 September 2027 |
Approval Documents
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Demarcation Of Plots 100% | Boundary Wall % not reported | Road Work 80% |
| Footpaths 76% | Water Supply Including Drinking Water Facilities 80% | Sewer System 80% |
| Drain 80% | Parks 80% | Tree Planting 100% |
| Design For Electric Supply Including Street Lighting 100% | Community Buildings 79% | Treatment And Disposal System Of Sewage And Sullage Water 80% |
| Solid Waste Management And Disposal System 100% | Water Conservation System 100% | Energy Management System Including Use Of Renewable Energy 73% |
| Fire Protection And Fire Safety System 100% | Social Infrastructure And Other Public Amenities Including Public Health Services % not reported | Emergency Evacuation Services % not reported |
| Other Miscellaneous Work % not reported |
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Cost (in Lacs) | ₹ 5,149 |
|---|---|
| Registration Fee | ₹ 59,000 |