View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Badhekar Suparn under registration P52100050130 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100050130
  • Project Name SUPARN
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Pune City
  • Village Pune (M Corp.)
  • Original Completion 31 December 2025
  • Revised Completion 31 December 2025
  • Project Area (in Sq.mt.) 551.0
  • Total Buildings/Towers 1
  • Documents 16 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 20 March 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Badhekar Properties

Promoters, Co-promoters & Members

NameRoleAddress
Murlidhar Kisanrao MoholPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SUPARN SUPARN CO OP HSG SOC 21 15 5 8 5 26 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 26
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 5 units · avg area 28.11 Sq.mt.
2 BHK 13 units · avg area 74.21 Sq.mt.
3 BHK 8 units · avg area 96.77 Sq.mt.
  • SUPARN CO OP HSG SOC
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 81.64 1 1
2BHK 82.4 1 1
3BHK 87.65 1 1
2BHK 90.39 1 0
3BHK 93.55 5 4
3BHK 104.14 1 0
3BHK 114.64 1 1
1RK 28.05 4 0
1RK 28.33 1 1
2BHK 53.23 1 1
2BHK 63.54 1 1
2BHK 65.58 1 1
2BHK 66.55 1 1
2BHK 69.39 1 1
2BHK 74.5 2 2
2BHK 80.82 1 1
2BHK 80.91 1 1
2BHK 81.24 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 40.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 30.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt 40.0% Fire Protection And Fire Safety Requirements 80.0%
Electrical Meter Room, Sub-station, Receiving Station 40.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SUPARN CO OP HSG SOC
SUPARN CO OP HSG SOC · Overall Progress 78%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
59 Form 1.Pdf
60 Form 2.Pdf
61 Form 3.Pdf
62 Disclosure Of Sold And Booked Inventory.Pdf
95 Withdrawal Update Form 1.Pdf
99 Withdrawal Update Form 2.Pdf
103 Withdrawal Update Form 3.Pdf
107 Form 2A (FY 2022 2023).Pdf
108 Form 2A (FY 2023 2024).Pdf
109 Form 2A (FY 2024 2025).Pdf
110 Form 2A (FY 2025 2026).Pdf
111 Form 5 (FY 2022 2023).Pdf
112 Form 5 (FY 2023 2024).Pdf
113 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0002388
Branch Address KOTHRUD