residential Under Construction Source: rera.mh

Destination EL Progreso RERA Details - P52100026761, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Destination EL Progreso under registration P52100026761 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100026761
  • Project Name DESTINATION EL PROGRESO
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Pimpri Chinchawad (M Corp.)
  • Original Completion 30 June 2024
  • Revised Completion 30 June 2024
  • Project Area (in Sq.mt.) 2,850.0
  • Total Buildings/Towers 1
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 22 October 2020 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name EL PROGRESO VENTURES
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
DESTINATION OSTIA216 1 B 2 DUDULGAON PUNE4263.42CompletedResidential / Group Housing2942017-10-312017-12-31NoNA

Promoters, Co-promoters & Members

NameRoleAddress
DHANANJAY VITTHAL KALBHORPartnerPune, MAHARASHTRA
JIJA CHOUDAMAN PATILPartnerPune, MAHARASHTRA
AJIT DAMODAR GAVHANEPartnerPune, MAHARASHTRA
NEWALE RAVINDRA MADHUKARPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
DESTINATION EL PROGRESO A BUILDING 0 66 16 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 112
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 80 units · avg area 56.38 Sq.mt.
3 BHK 24 units · avg area 66.55 Sq.mt.
Shop 8 units · avg area 14.55 Sq.mt.
  • A BUILDING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3BHK 66.18 11 7
2BHK 54.32 13 4
3BHK 66.87 13 7
2BHK 57.77 13 0
2BHK 52.47 2 0
2BHK 57.52 13 0
Shop 22.08 1 0
Shop 13.87 5 0
Shop 12.49 2 0
2BHK 55.77 13 13
2BHK 56.9 13 4
2BHK 56.62 13 5
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 90.0%
Storm Water Drains 95.0% Landscaping & Tree Planting 50.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 50.0% Solid Waste Management And Disposal 95.0%
Water Conservation /Rain Water Harvesting 80.0% Energy Managemcnt 50.0% Fire Protection And Fire Safety Requirements 50.0%
Electrical Meter Room, Sub-station, Receiving Station 10.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A BUILDING
A BUILDING · Overall Progress 58%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Complete
% Work100%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work85%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work79%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank KALLAPPANNA AWADE ICHALKARANJI JANATA SAHAKARI BANK LIMITED
IFSC KAIJ0000039
Branch Address BHOSARI
Country/City