- RERA Number P52100050302
- Project Name OJAS EYRIE PHASE - 1
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Pune
- Taluka Mawal
- Village Lonavala (M Cl)
- Original Completion 31 December 2025
- Project Area (in Sq.mt.) 8,100.00
- Total Buildings/Towers 4
- Documents 33 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| OJAS NESTHOMES PRIVATE LIMITED THROUGHT DIRECTOR SANDEEP JAIN | Authorized Signatory |
| SANJEEV KISHANKISHOR MAHAJAN | Authorized Signatory |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| OJAS EYRIE PHASE - 1 | A 3 | 2025-12-31 | 0 | 1 | 0 | 2 | 1 | 0 | 12 |
| OJAS EYRIE PHASE - 1 | E | 2025-12-31 | 0 | 1 | 0 | 1 | 1 | 0 | 2 |
| OJAS EYRIE PHASE - 1 | F | 2025-12-31 | 0 | 1 | 0 | 1 | 1 | 0 | 14 |
| OJAS EYRIE PHASE - 1 | G | 2025-12-31 | 0 | 1 | 0 | 1 | 1 | 6 | 4 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- A 3
- E
- F
- G
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2BHK | 49.20 | 6 | 0 |
| 2BHK | 49.40 | 6 | 0 |
| 2BHK | 51.50 | 6 | 0 |
| 2BHK | 52 | 6 | 0 |
| 2BHK | 51.80 | 12 | 0 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| Bungalow | 120.04 | 2 | 0 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| Bungalow | 120.80 | 1 | 0 |
| Bungalow | 124.20 | 1 | 0 |
| Bungalow | 161.40 | 1 | 0 |
| Shop | 62.10 | 1 | 0 |
| Shop | 52.70 | 1 | 0 |
| Bungalow | 79.10 | 1 | 0 |
| Bungalow | 83.30 | 1 | 0 |
| Bungalow | 118.80 | 3 | 0 |
| Shop | 22.10 | 1 | 0 |
| Shop | 21.70 | 1 | 0 |
| Shop | 14.50 | 1 | 0 |
| Bungalow | 119.60 | 1 | 0 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| Bungalow | 124.60 | 2 | 0 |
| Bungalow | 119.20 | 2 | 0 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 26 | 0 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths % not reported | Water Conservation Rainwater Harvesting % not reported | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements % not reported | Electrical Meter Room Substation Receivingstation % not reported | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking % not reported | Water Supply % not reported | Sewerage % not reported |
| Storm Water Drains % not reported | Landscaping Tree Planting % not reported | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- A 3
- E
- F
- G
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | BANK OF MAHARASHTRA |
|---|---|
| IFSC | MAHB0000075 |