residential Under Construction Source: rera.mh

Harivishva Infinia RERA Details - P52100052385, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Harivishva Infinia under registration P52100052385 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100052385
  • Project Name HARIVISHVA INFINIA PHASE 2
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Pune
  • Taluka Mulshi
  • Village Tathwade
  • Original Completion 31 December 2027
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 7,400.0
  • Total Buildings/Towers 1
  • Documents 9 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 21 August 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name HARIVISHVA DEVELOPERS LLP

Promoters, Co-promoters & Members

NameAddress
PRASHANT TUKARAM GAIKWADY0wRpGYOz8YHhpstl3YmxF9Xrx5K5MCj9epfox1BpkMOXzbzQmvV2U5g09uG0vnc, Pune, MAHARASHTRA
HARISH NIVRUTTI NAVALEPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
HARIVISHVA INFINIA PHASE 2 B Wing 205 161 28 28 18 205 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 205
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 183 units · avg area 67.92 Sq.mt.
3 BHK 22 units · avg area 87.07 Sq.mt.
  • B Wing
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 71.5 25 19
2BHK 66.66 4 4
3BHK 82.7 1 1
2BHK 64.14 25 24
3BHK 87.28 21 20
2BHK 67.22 25 24
2BHK 68.19 104 91
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 50.0%
Storm Water Drains 35.0% Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings 50.0% Treatment And Disposal Of Sewage And Sullage Water 60.0% Solid Waste Management And Disposal 50.0%
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 20.0%
Electrical Meter Room, Sub-station, Receiving Station 70.0% Aggregate Area Of Recreational Open Space 10.0% Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • B Wing
B Wing · Overall Progress 63%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work60%
Sanitary Fittings within the flats / premises
In Progress
% Work50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
110 Withdrawal Update Form 1.Pdf
112 Withdrawal Update Form 2.Pdf
114 Withdrawal Update Form 3.Pdf
116 Form 2A (FY 2023 2024).Pdf
117 Form 2A (FY 2024 2025).Pdf
118 Form 5 (FY 2023 2024).Pdf
119 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0004887
Branch Address Wakad Branch
Country/City