RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100019736
- Project Name Panache
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Pune
- Taluka Mulshi
- Village Wakad
- Original Completion 30 December 2023
- Project Area (in Sq.mt.) 3,220.00
- Total Buildings/Towers 1
- Documents 74 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Survey Number S No 108/1/2, Marunjee Road,Behind Akshra School,,Vinode Wasti Wakad 411057 | |
Boundary Details |
|
| Boundaries East ADJ SURVEY NO 108 | Boundaries West MARUNJI VILLAGE BOUNDRY |
| Boundaries South ADJ SURVEY NO 108 | Boundaries North 30 MTR WIDE PROPOSED D P ROAD |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| Panache | A | 2022-12-31 | 2 | 1 | 0 | 15 | 0 | 21 | 71 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- A
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2BHK | 61.15 | 2 | 2 |
| 2BHK | 61.18 | 1 | 1 |
| 2BHK | 61.85 | 1 | 0 |
| 2BHK | 62.55 | 1 | 1 |
| 2BHK | 62.6 | 3 | 3 |
| 2BHK | 62.65 | 1 | 1 |
| 2BHK | 62.66 | 1 | 1 |
| 2BHK | 61.78 | 2 | 0 |
| 2BHK | 60.4 | 1 | 1 |
| 2BHK | 60.47 | 1 | 1 |
| 2BHK | 60.48 | 1 | 1 |
| 2BHK | 61.07 | 1 | 1 |
| 2BHK | 63.91 | 11 | 10 |
| 2BHK | 63.92 | 1 | 1 |
| 2BHK | 64.22 | 1 | 1 |
| 2BHK | 64.39 | 1 | 1 |
| 2BHK | 64.4 | 5 | 5 |
| 2BHK | 64.41 | 1 | 1 |
| 2BHK | 64.45 | 1 | 1 |
| 2BHK | 64.6 | 2 | 2 |
| 2BHK | 64.62 | 2 | 2 |
| 2BHK | 64.66 | 4 | 4 |
| 2BHK | 65.1 | 1 | 1 |
| 2BHK | 65.11 | 2 | 2 |
| 2BHK | 65.13 | 1 | 1 |
| 2BHK | 65.49 | 1 | 1 |
| 2BHK | 65.85 | 1 | 1 |
| 2BHK | 65.86 | 1 | 1 |
| 2BHK | 65.89 | 1 | 1 |
| 2BHK | 65.92 | 1 | 1 |
| 2BHK | 65.93 | 1 | 1 |
| 2BHK | 65.94 | 4 | 4 |
| 2BHK | 66.08 | 1 | 1 |
| 2BHK | 66.58 | 1 | 1 |
| 2BHK | 66.61 | 1 | 1 |
| 2BHK | 66.78 | 1 | 1 |
| 2BHK | 66.88 | 4 | 4 |
| 2BHK | 66.92 | 1 | 1 |
| 2BHK | 67.16 | 3 | 3 |
| Shop | 66.47 | 1 | 0 |
| ConferenceHall | 70.93 | 1 | 0 |
| Shop | 74.94 | 1 | 0 |
| 2BHK | 80.76 | 1 | 0 |
| Shop | 82.28 | 1 | 0 |
| Shop | 82.65 | 1 | 0 |
| RefugeeArea | 88.34 | 1 | 0 |
| Shop | 97.05 | 1 | 0 |
| Shop | 97.42 | 1 | 0 |
| 4BHK | 129.58 | 6 | 6 |
| 3BHK | 175.01 | 1 | 1 |
| 3BHK | 179.18 | 1 | 1 |
| 3BHK | 189.82 | 1 | 1 |
| 3BHK | 179.82 | 1 | 1 |
| 2BHK | 61.86 | 4 | 1 |
| 2BHK | 62.34 | 1 | 1 |
| 2BHK | 62.54 | 4 | 4 |
| 2BHK | 62.83 | 2 | 2 |
| 2BHK | 62.84 | 1 | 1 |
| 2BHK | 63.38 | 2 | 2 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 0 | 34 | 88 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 100% | Water Conservation Rainwater Harvesting 100% | Energy Management 100% |
| Fire Protection And Fire Safety Requirements 100% | Electrical Meter Room Substation Receivingstation 100% | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking % not reported | Water Supply 100% | Sewerage 100% |
| Storm Water Drains 100% | Landscaping Tree Planting 100% | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- A
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | CANARA BANK |
|---|---|
| IFSC | CNRB0015350 |