Puranik Sayama RERA Details - P52100005004, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Puranik Sayama under registration P52100005004 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100005004
  • Project Name Sayama Phase 4
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Mawal
  • Village Lonavala (M Cl)
  • Original Completion 30 December 2036
  • Revised Completion 30 December 2036
  • Project Area (in Sq.mt.) 10,226.36
  • Total Buildings/Towers 18
  • Documents 7 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2036 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2036 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Puranik Builders Limited
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Aldea AnnexoAldea Annexo Next to Hotel Vits Nr Balewadi Stadium Mhalunge Pune 41104512511CompletedResidential / Group Housing21292016-12-312017-04-29NoNA
Puranik City Part AKasarvadavali Ghodbunder Road Thane west 40061512080CompletedResidential / Group Housing21082012-12-312013-02-21NoNA
Puranik City Part BKasarvadavali Ghodbunder Road Thane west 40061512080CompletedResidential / Group Housing2802011-12-312012-04-21NoNA
Hometown Part AKasarvadavali Ghodbunder Road Thane west 40061523110CompletedResidential / Group Housing21762013-06-302013-11-06NoNA
Hometown Part BKasarvadavali Ghodbunder Road Thane west 40061523110CompletedResidential / Group Housing41592014-08-312015-01-20NoNA
Hometown Part CKasarvadavali Ghodbunder Road Thane west 40061523110CompletedResidential / Group Housing11082016-12-312017-04-26NoNA

Promoters, Co-promoters & Members

NameRoleAddress
Shailesh Gopal PuranikManaging DirectorThane, MAHARASHTRA
Yogesh Govind PuranikDirectorThane, MAHARASHTRA
Shrikant Govind PuranikDirectorThane, MAHARASHTRA
Nilesh Ravindra PuranikDirectorThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Sayama Phase 4 Building 2 Villa 5 to 8 0 4 16 0 0 NA
Sayama Phase 4 Building 3 Villa 9 and 10 0 2 8 0 0 NA
Sayama Phase 4 Building 4 Villa 11 to 14 0 4 16 0 0 NA
Sayama Phase 4 Building 5 Villa 15 to 18 0 4 16 0 0 NA
Sayama Phase 4 Building 6 Villa 19 to 21 0 3 12 0 0 NA
Sayama Phase 4 Building 7 Villa 22 and 23 0 2 8 0 0 NA
Sayama Phase 4 Building 19 Villa 64 to 67 0 4 16 0 0 NA
Sayama Phase 4 Building 20 Villa 68 to 71 0 4 16 0 0 NA
Sayama Phase 4 Building 23 Villa 80 to 83 0 4 16 0 0 NA
Sayama Phase 4 Building 24 Villa 84 to 87 0 4 16 0 0 NA
Sayama Phase 4 Building 28 Villa 98 to 101 0 4 16 0 0 NA
Sayama Phase 4 Building 29 Villa 102 to 105 0 4 16 0 0 NA
Sayama Phase 4 Building 30 Villa 106 to 109 0 4 16 0 0 NA
Sayama Phase 4 Building 31 Villa 110 to 113 0 4 16 0 0 NA
Sayama Phase 4 Building 33 Villa 118 to 121 0 4 16 0 0 NA
Sayama Phase 4 Building 34 Villa 122 to 125 0 4 16 0 0 NA
Sayama Phase 4 Building 38 Villa 136 to 139 0 4 16 0 0 NA
Sayama Phase 4 Building 39 Villa 140 to 143 0 4 16 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 75.0% Water Supply 75.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 75.0%
Storm Water Drains 75.0% Landscaping & Tree Planting 30.0% Street Lighting 40.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 45.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 45.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Building 2 Villa 5 to 8
  • Building 3 Villa 9 and 10
  • Building 4 Villa 11 to 14
  • Building 5 Villa 15 to 18
  • Building 6 Villa 19 to 21
  • Building 7 Villa 22 and 23
  • Building 19 Villa 64 to 67
  • Building 20 Villa 68 to 71
  • Building 23 Villa 80 to 83
  • Building 24 Villa 84 to 87
  • Building 28 Villa 98 to 101
  • Building 29 Villa 102 to 105
  • Building 30 Villa 106 to 109
  • Building 31 Villa 110 to 113
  • Building 33 Villa 118 to 121
  • Building 34 Villa 122 to 125
  • Building 38 Villa 136 to 139
  • Building 39 Villa 140 to 143
Building 2 Villa 5 to 8 · Overall Progress 0%
Stilt Floor
Not Started
% Work0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
71 Form 1.Pdf
72 Form 2.Pdf
73 Form 3.Pdf
74 Disclosure Of Sold And Booked Inventory.Pdf
87 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0001440
Branch Address Shop No G 115, 116, 117, 118, High street cum Highland Corporate Centre, Kapurbawadi Junction, Thane