RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100002848
- Project Name RAVINANDA TRINITY
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Pune
- Taluka Haveli
- Village WAGHOLI
- Original Completion 01 January 2021
- Revised Completion 01 July 2022
- Project Area (in Sq.mt.) 13,700
- Total Buildings/Towers 3
- Documents 80 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 192 | 95 |
| Covered Parking | 134 | 37 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 95% | Water Conservation Rainwater Harvesting 80% | Energy Management 80% |
| Fire Protection And Fire Safety Requirements 60% | Electrical Meter Room Substation Receivingstation 90% | Aggregate Area Of Recreational Open Space 90% |
| Open Parking % not reported | Water Supply 80% | Sewerage 80% |
| Storm Water Drains % not reported | Landscaping Tree Planting 80% | Street Lighting 90% |
| Community Buildings 90% | Treatment And Disposal Of Sewage Sullage Water 80% | Solid Waste Management Disposal 80% |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | Bank Of Maharashtra |
|---|---|
| IFSC | MAHB0001140 |