Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential New Launch Source: rera.mh

RK Ikra Tower RERA Details - PM1260002500998, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for RK Ikra Tower under registration PM1260002500998 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PM1260002500998
  • Project Name IKRA TOWER
  • Project Type Mixed
  • Project Status New Launch
  • State Maharashtra
  • District Pune
  • Taluka Baramati
  • Village Baramati (M Cl)
  • Original Completion 30 December 2027
  • Revised Completion 30 December 2027
  • Project Area (in Sq.mt.) 557.62
  • Total Buildings/Towers 1
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 29 September 2025 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name RK INFRA

Promoters, Co-promoters & Members

NameRoleAddress
Vanita Chandrashekhar GadhavePartnerPune, MAHARASHTRA
Chandrashekhar Ashok GadhavePartnerPune, MAHARASHTRA
Shabina Ajaj KhanPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
IKRA TOWER IKRA TOWER 25 7 7 7 19 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Street Lighting % not reported Community Buildings % not reported Internal Roads & Footpaths % not reported
Water Supply 40.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported Storm Water Drains % not reported
Landscaping & Tree Planting % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • IKRA TOWER
IKRA TOWER · Overall Progress 62%
Stilt Floor
In Progress
% Work80%
Excavation
Complete
% Work100%
Basement (if any)
In Progress
% Work80%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work40%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank THE COSMOS CO OPERATIVE BANK LIMITED
IFSC COSB0000014
Branch Address GALA NO.1, CTS NO.612, D.A.SATAV COMPLEX,OPP. NAIGAONKAR HOSPITAL, SILVER JUBILEE HOSPITAL ROAD, BARAMATI 413 102.
Country/City