Samarth Swamini Heights RERA Details - P52100045233, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Samarth Swamini Heights under registration P52100045233 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100045233
  • Project Name Swamini Heights
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Pune
  • Taluka Indapur
  • Village Bhigvan
  • Original Completion 31 December 2027
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 2,000.0
  • Total Buildings/Towers 1
  • Documents 9 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 10 May 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Samarth Developers Nirmit Swamini Heights

Promoters, Co-promoters & Members

NameRoleAddress
Pravin Bhimrao waghDirectorPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Swamini Heights Swamini Heights Wing A,B,C,D 0 0 5 5 5 28 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 56
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 16 units · avg area 44.82 Sq.mt.
2 BHK 40 units · avg area 63.22 Sq.mt.
  • Swamini Heights Wing A,B,C,D
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 65.36 4 0
2BHK 64.89 4 0
1BHK 44.97 4 0
2BHK 62.49 4 0
1BHK 44.75 4 0
2BHK 59.26 4 0
1BHK 44.82 4 0
2BHK 59.12 4 0
2BHK 65.47 4 0
2BHK 64.18 4 0
2BHK 65.36 4 0
2BHK 64.89 4 0
2BHK 61.22 4 0
1BHK 44.75 4 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Swamini Heights Wing A,B,C,D
Swamini Heights Wing A,B,C,D · Overall Progress 89%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
28 Form 2A (FY 2024 2025).Pdf
29 Form 2A (FY 2023 2024).Pdf
30 Form 2A (FY 2022 2023).Pdf
31 Form 2A (FY 2025 2026).Pdf
32 Form 5 (FY 2024 2025).Pdf
33 Form 5 (FY 2023 2024).Pdf
34 Form 5 (FY 2022 2023).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF MAHARASHTRA
IFSC MAHB0000463
Branch Address Near Bus Station Pune Solapur Road Bhigwan Indapur Bhigwan
Country/City