residential Ready to Move Source: rera.mh

Shivtej Kashi Vishveshwar Park RERA Details - P52100032491, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shivtej Kashi Vishveshwar Park under registration P52100032491 in Pune, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100032491
  • Project Name KASHIVISHVESHWAR PARK
  • Project Type Plots
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Pune
  • Taluka Baramati
  • Village Baramati (M Cl)
  • Original Completion 23 July 2025
  • Project Area (in Sq.mt.) 13,800
  • Documents 18 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 10 January 2022 Expected commencement of civil works and foundation on site.
Original Completion 23 July 2025 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SHIVTEJ DEVELOPERS
Other Description NA

Promoters, Co-promoters & Members

NameRole
SUNIL ANANTA PAWARPartner
SAGAR BALU SHINDEAuthorized Signatory
VIRAT VASANT TAWAREPartner
ANIL BABAN KADAMPartner
RAHUL BALASAHEB TARUPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 100% Water Conservation Rainwater Harvesting % not reported Energy Management % not reported
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room Substation Receivingstation 50% Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply % not reported Sewerage 100%
Storm Water Drains % not reported Landscaping Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
2 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
2 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval / NA Order For Plotted Development
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
1 Engineer’S Certificate On Cost Incurred On Project (Form 2)
1 CERSAI Details
2 CERSAI Details
1 Proforma Of Allotment Letter
1 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK LTD
IFSC IBKL0000520
Country/City